06/22/2023 - Construction Update

* Intersection full closure (24/7) will start the morning of Wednesday July 5th and is anticipated to last until the beginning of August *

* Businesses will remain open and parking will be maintained along Main St for access to businesses at the intersection *


Work Completed between 06/15/23 and 06/21/23:

Dry Utilities:

  • Finalized JUT
  • Pouring of signal bases for new signal poles at each corner of the intersection

Concrete Curb, Gutter, and Sidewalks:

  • Demolition of existing sidewalks, curb, and parking
  • Staking of sidewalk and curb locations




06/16/23 - Pouring of concrete for new signal base at the southwest corner of the intersection, in front of NAPA.


06/19/23 - Making signal connections to new signal foundation at the southwest corner of the intersection, in front of NAPA.




Work in Progress 06/22/23 to 06/28/23:

Dry Utilities:

  • Temporary Signal Pole installation
  • Finalize signal connections

Concrete Curb, Gutter, and Sidewalks:

  • Pour of sidewalks, curb, and gutter


Upcoming Work between 06/29/23 to 07/05/23:

Concrete Curb, Gutter, and Sidewalks:

  • Finish pouring of sidewalks, curb, and gutter

* There will be no work on Tuesday July 4th – Fourth of July Holiday *

Categories: Construction Update
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>