07/06/2023 - Construction Update

*Intersection is currently fully closed, and will last for approximately 4 weeks*


Work Completed between 06/29/23 and 07/05/23:

Intersection:

  • Installation of temporary parking along Main St for business access
  • Start of intersection demolition



06/28/23: Finishing of newly constructed ADA curb ramp at the northeast corner of Main St and Wood Ave.


06/29/23: Forming of curb along the south side of Main St in front of the Dairy Freeze.



Work in Progress between 07/06/23 and 07/12/23:

Sidewalks, Curb, and Gutter:

  • Finish forming and pouring of curb and gutter
  • Finish sidewalk pours

Intersection:

  • Complete demolition of intersection
  • Grade intersection
  • Start form and pour of intersection

Wood Ave and Main St Approaches:

  • Demolition of south leg of Wood Ave



Upcoming Work between 07/13/23 and 07/19/23:

Intersection:

  • Continuing to form and pour the intersection

Wood Ave and Main St Approaches:

  • Grade south leg of Wood Ave
  • Demo and grade west leg of Main St