07/06/2023 - Construction Update
*Intersection is currently fully closed, and will last for approximately 4 weeks*
Work Completed between 06/29/23 and 07/05/23:
Intersection:
- Installation of temporary parking along Main St for business access
- Start of intersection demolition
06/28/23: Finishing of newly constructed ADA curb ramp at the northeast corner of Main St and Wood Ave.
06/29/23: Forming of curb along the south side of Main St in front of the Dairy Freeze.
Work in Progress between 07/06/23 and 07/12/23:
Sidewalks, Curb, and Gutter:
- Finish forming and pouring of curb and gutter
- Finish sidewalk pours
Intersection:
- Complete demolition of intersection
- Grade intersection
- Start form and pour of intersection
Wood Ave and Main St Approaches:
- Demolition of south leg of Wood Ave
Upcoming Work between 07/13/23 and 07/19/23:
Intersection:
- Continuing to form and pour the intersection
Wood Ave and Main St Approaches:
- Grade south leg of Wood Ave
- Demo and grade west leg of Main St
![<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>](http://d2gu4vothxmtom.cloudfront.net/assets/ajax-loader-transparent-aebc793d0064383ee6b1625bf3bb32532ec30a5c12bf9117066107d412119123.gif)