06/15/2023 - Construction Update
Work Completed between 06/08/23 and 06/14/23:
Sewer:
- Finalized all connections
Dry Utilities:
- Continued work on the Joint Utility Trench (JUT) and signal connections
Concrete Curb, Gutter, and Sidewalks:
- Demolition and grading in preparation of pouring of sidewalks
06/12/23 - Mayor Kathy Hayden on site holding conduit for the Joint Utility Trench (JUT).
06/13/23 - Front of the Dairy Freeze after the asphalt was removed to prepare for the construction of new sidewalks.
Work in Progress this Week between 06/15/23 and 06/21/23:
Dry Utilities:
- Finalize JUT and signal connections
- Installation of temporary signal pole to allow for space for the new signal base
- Pouring bases for new signal poles
Concrete Curb, Gutter, and Sidewalks:
- Finalize demolition of sidewalks
- Staking of sidewalk locations
- Pouring of sidewalks
Upcoming Work between 06/22/23 and 06/28/23:
Concrete Curb, Gutter, and Sidewalks:
- Continuation of sidewalk pouring