Stewart Road/8th Street White River Bridge
Location: Stewart Road at the White River
Project Completion: 2027
Description: This project will replace existing 2-lane bridge with a new 74-foot wide bridge with two unequal length spans. The new structure will accommodate 4 vehicle lanes, a sidewalk, and a trail crossing.
Benefits: The new bridge will alleviate the current bottleneck in the corridor to allow better traffic flow. The bridge will also support safe pedestrian movement across the bridge and connect to existing pedestrian facilities.
Existing Conditions Looking East
Proposed Conditions Looking East


Location: Stewart Road at the White River
Project Completion: 2027
Description: This project will replace existing 2-lane bridge with a new 74-foot wide bridge with two unequal length spans. The new structure will accommodate 4 vehicle lanes, a sidewalk, and a trail crossing.
Benefits: The new bridge will alleviate the current bottleneck in the corridor to allow better traffic flow. The bridge will also support safe pedestrian movement across the bridge and connect to existing pedestrian facilities.
Existing Conditions Looking East
Proposed Conditions Looking East


-
04/03/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 04/04/2026:
- Completed CSBC placement
- Completed joint utility trench
- Placed HMA pavement on east and west approach slabs
- Installed temporary traffic barrier
- Traffic will switch over on to the new bridge between 11:30pm Friday, April 4th and 1 AM Saturday, April 5th.
WORK IN PROGRESS NEXT WEEK (04/05/2026 - 04/11/2026):
- Begin demo work on old bridge
UPCOMING WORK THROUGH 04/30/2026:
- Begin demo of old bridge.
- Utility work
Placing HMA Pavement on East Ramp
Removing Roadway at Butte Avenue for Grade Tie-in to West Approach Ramp -
03/27/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 03/28/2026:
- Install CSBC at approaches
- Prepped for roadway paving
- Butte Avenue closing at Stewart Road from Saturday 3/28 to Monday 3/30
WORK IN PROGRESS NEXT WEEK (03/29/2026 - 04/04/2026):
- Continue work on approach ramps
- Butte Avenue closing at Stewart Road from Saturday 3/28 to Monday 3/30
- Traffic will switch on to the new bridge section on April 4th
UPCOMING WORK THROUGH 04/30/2026:
- Begin demo of old bridge.
- Utility work
- Work on east and west approach ramps
- Traffic will switch on to the new bridge section on the first week of April
Install CSBC on approach slab
Roadway tining of the new bridge deck -
03/20/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 03/21/2026:
- Completed bridge deck tining
- Completed final waterline tie-in
- Prepped for roadway paving
- Completed joint utility trench tie-ins
WORK IN PROGRESS NEXT WEEK (03/22/2026 - 03/28/2026):
- Continue work on approach ramps
- Complete subgrade for roadway paving
UPCOMING WORK THROUGH 03/31/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
- Traffic will switch on to the new bridge section on the first week of April
Sawcutting in Tining on Bridge Deck
Joint Utility Trench Tie-In -
03/13/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 03/14/2026:
- Completed north concrete pedestrian barrier
- Pressure and purity tested new waterline
- Prepped for roadway paving
WORK IN PROGRESS NEXT WEEK (03/15/2026 - 03/21/2026):
- Complete joint utility trench
- Continue work on approach ramps
- Complete water utility tie-ins
- Complete subgrade for roadway paving
UPCOMING WORK THROUGH 03/31/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
- Traffic will switch on to the new bridge section on the first week of April
Installing North Pedestrian Barrier
Installing North Pedestrian Barrier -
03/06/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 03/07/2026:
- Continued utility installation
- Completed installation of illumination conduit
- Installed and weld expansion joint at east approach
WORK IN PROGRESS NEXT WEEK (03/08/2026 - 03/15/2026):
- Place north pedestrian barrier
- Continue work on approach ramps
- Complete water utility installation under the bridge
- Prep for roadway paving
UPCOMING WORK THROUGH 03/31/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
Placing Roadway Subgrade at West Approach
Installing Illumination Conduit -
02/27/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 02/28/2026:
- Continued utility installation under the bridge
- Continue installation of illumination conduit
- Installed and weld expansion joint at east approach
WORK IN PROGRESS NEXT WEEK (03/01/2026 - 03/07/2026):
- Continue installation of illumination conduit
- Continue work on approach ramps
- Continue water utility installation under the bridge
UPCOMING WORK THROUGH 03/31/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
Clean and Install Expansion Joint at East Approach
Installing Water Line and Valves at East Approach -
02/20/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 02/21/2026:
- Continued utility installation under the bridge
- Poured concrete east approach ramp
WORK IN PROGRESS NEXT WEEK (02/22/2026 - 02/28/2026):
- Continue installation of illumination conduit
- Continue work on approach ramps
- Continue water utility installation under the bridge
UPCOMING WORK THROUGH 02/28/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
Joint Utility Trench Coming out of Bridge Substructure
Water Line comin gout of Bridge Substructure -
02/13/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 02/14/2026:
- Continued utility installation under the bridge
- Completed surcharge material removal
- Continued approach ramp work
WORK IN PROGRESS NEXT WEEK (02/15/2026 - 02/21/2026):
- Continue installation of illumination conduit
- Continue work on approach ramps
- Complete utility installation under the bridge
UPCOMING WORK THROUGH 02/28/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
Joint Utility Trench Under New Bridge
Placing Approach Slab Concrete -
02/06/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 02/07/2026:
- Continued utility installation under the bridge
- Continued surcharge material removal
- Continued approach ramp work
WORK IN PROGRESS NEXT WEEK (02/08/2026 - 02/14/2026):
- Complete surcharge removal
- Continue work on approach ramps
- Complete utility installation under the bridge
UPCOMING WORK THROUGH 02/28/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
Removing cure blankets of concrete bridge deck
Completed subgrade on west approach ramp -
01/30/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 01/31/2026:
- Continued utility installation under the bridge
- Continued surcharge material removal
- Continued approach ramp work
WORK IN PROGRESS NEXT WEEK (02/01/2026 - 02/07/2026):
- Complete surcharge material removal
- Pour concrete approach ramps
- Continued utility installation under the bridge
UPCOMING WORK THROUGH 02/28/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
Surcharge Material Removal at West Approach Ramp
Life Cycle
-
Preliminary Design
Stewart Road/8th Street White River Bridge has finished this stage2013-2021 Conceptual Design, Initial environmental permitting
-
Final Design & Right of Way
Stewart Road/8th Street White River Bridge has finished this stage2021-2024 Wrap up environmental permitting, finalize design for the new bridge, and secure right-of-way.
-
Construction 2024-2028
Stewart Road/8th Street White River Bridge is currently at this stageConstruction of the new bridge expected to take up to 3.5 years, based on salmon migration restrictions on construction in-water work.
Funding
TOTAL PROJECT:
$ 30 Million
DESIGN AND RIGHT-OF-WAY ACQUISITION: $5 Million, Fully Funded
CONSTRUCTION: $25 Million, Fully Funded
Funding Partners:
- Congressional Appropriation through Representative Strickland's office
- Federal (STP, NHFP)
- Washington State Transportation Improvement Board (TIB)
- Pierce County
- Freight Mobility Strategic Investment Board (FMSIB)
- City of Auburn
- Port of Tacoma
- City of Sumner
Who's listening
-
Phone 253-299-5709 Email michaelk@sumnerwa.gov -
Phone 253-299-5711 Email andrewl@sumnerwa.gov