Stewart Road/8th Street White River Bridge

Location: Stewart Road at the White River

Project Completion: 2027

Description: This project will replace existing 2-lane bridge with a new 74-foot wide bridge with two unequal length spans. The new structure will accommodate 4 vehicle lanes, a sidewalk, and a trail crossing.

Benefits: The new bridge will alleviate the current bottleneck in the corridor to allow better traffic flow. The bridge will also support safe pedestrian movement across the bridge and connect to existing pedestrian facilities.

Existing Conditions Looking East Proposed Conditions Looking East



Map showing project area on Stewart Rd/8th Street over White River.


Location: Stewart Road at the White River

Project Completion: 2027

Description: This project will replace existing 2-lane bridge with a new 74-foot wide bridge with two unequal length spans. The new structure will accommodate 4 vehicle lanes, a sidewalk, and a trail crossing.

Benefits: The new bridge will alleviate the current bottleneck in the corridor to allow better traffic flow. The bridge will also support safe pedestrian movement across the bridge and connect to existing pedestrian facilities.

Existing Conditions Looking East Proposed Conditions Looking East



Map showing project area on Stewart Rd/8th Street over White River.


  • 04/03/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 04/04/2026:

    • Completed CSBC placement
    • Completed joint utility trench
    • Placed HMA pavement on east and west approach slabs
    • Installed temporary traffic barrier
    • Traffic will switch over on to the new bridge between 11:30pm Friday, April 4th and 1 AM Saturday, April 5th.

    WORK IN PROGRESS NEXT WEEK (04/05/2026 - 04/11/2026):

    • Begin demo work on old bridge

    UPCOMING WORK THROUGH 04/30/2026:

    • Begin demo of old bridge.
    • Utility work


    Placing HMA Pavement on East Ramp

    Removing Roadway at Butte Avenue for Grade Tie-in to West Approach Ramp

  • 03/27/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 03/28/2026:

    • Install CSBC at approaches
    • Prepped for roadway paving
    • Butte Avenue closing at Stewart Road from Saturday 3/28 to Monday 3/30

    WORK IN PROGRESS NEXT WEEK (03/29/2026 - 04/04/2026):

    • Continue work on approach ramps
    • Butte Avenue closing at Stewart Road from Saturday 3/28 to Monday 3/30
    • Traffic will switch on to the new bridge section on April 4th

    UPCOMING WORK THROUGH 04/30/2026:

    • Begin demo of old bridge.
    • Utility work
    • Work on east and west approach ramps
    • Traffic will switch on to the new bridge section on the first week of April


    Install CSBC on approach slab

    Roadway tining of the new bridge deck

  • 03/20/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 03/21/2026:

    • Completed bridge deck tining
    • Completed final waterline tie-in
    • Prepped for roadway paving
    • Completed joint utility trench tie-ins

    WORK IN PROGRESS NEXT WEEK (03/22/2026 - 03/28/2026):

    • Continue work on approach ramps
    • Complete subgrade for roadway paving

    UPCOMING WORK THROUGH 03/31/2026:

    • Work will continue on new bridge substructure and bridge deck.
    • Utility work
    • Work on east and west approach ramps
    • Traffic will switch on to the new bridge section on the first week of April


    Sawcutting in Tining on Bridge Deck


    Joint Utility Trench Tie-In

  • 03/13/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 03/14/2026:

    • Completed north concrete pedestrian barrier
    • Pressure and purity tested new waterline
    • Prepped for roadway paving

    WORK IN PROGRESS NEXT WEEK (03/15/2026 - 03/21/2026):

    • Complete joint utility trench
    • Continue work on approach ramps
    • Complete water utility tie-ins
    • Complete subgrade for roadway paving

    UPCOMING WORK THROUGH 03/31/2026:

    • Work will continue on new bridge substructure and bridge deck.
    • Utility work
    • Work on east and west approach ramps
    • Traffic will switch on to the new bridge section on the first week of April


    Installing North Pedestrian Barrier

    Installing North Pedestrian Barrier

  • 03/06/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 03/07/2026:

    • Continued utility installation
    • Completed installation of illumination conduit
    • Installed and weld expansion joint at east approach

    WORK IN PROGRESS NEXT WEEK (03/08/2026 - 03/15/2026):

    • Place north pedestrian barrier
    • Continue work on approach ramps
    • Complete water utility installation under the bridge
    • Prep for roadway paving

    UPCOMING WORK THROUGH 03/31/2026:

    • Work will continue on new bridge substructure and bridge deck.
    • Utility work
    • Work on east and west approach ramps


    Placing Roadway Subgrade at West Approach


    Installing Illumination Conduit

  • 02/27/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 02/28/2026:

    • Continued utility installation under the bridge
    • Continue installation of illumination conduit
    • Installed and weld expansion joint at east approach

    WORK IN PROGRESS NEXT WEEK (03/01/2026 - 03/07/2026):

    • Continue installation of illumination conduit
    • Continue work on approach ramps
    • Continue water utility installation under the bridge

    UPCOMING WORK THROUGH 03/31/2026:

    • Work will continue on new bridge substructure and bridge deck.
    • Utility work
    • Work on east and west approach ramps


    Clean and Install Expansion Joint at East Approach

    Installing Water Line and Valves at East Approach

  • 02/20/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 02/21/2026:

    • Continued utility installation under the bridge
    • Poured concrete east approach ramp

    WORK IN PROGRESS NEXT WEEK (02/22/2026 - 02/28/2026):

    • Continue installation of illumination conduit
    • Continue work on approach ramps
    • Continue water utility installation under the bridge

    UPCOMING WORK THROUGH 02/28/2026:

    • Work will continue on new bridge substructure and bridge deck.
    • Utility work
    • Work on east and west approach ramps


    Joint Utility Trench Coming out of Bridge Substructure

    Water Line comin gout of Bridge Substructure

  • 02/13/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 02/14/2026:

    • Continued utility installation under the bridge
    • Completed surcharge material removal
    • Continued approach ramp work

    WORK IN PROGRESS NEXT WEEK (02/15/2026 - 02/21/2026):

    • Continue installation of illumination conduit
    • Continue work on approach ramps
    • Complete utility installation under the bridge

    UPCOMING WORK THROUGH 02/28/2026:

    • Work will continue on new bridge substructure and bridge deck.
    • Utility work
    • Work on east and west approach ramps


    Joint Utility Trench Under New Bridge

    Placing Approach Slab Concrete

  • 02/06/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 02/07/2026:

    • Continued utility installation under the bridge
    • Continued surcharge material removal
    • Continued approach ramp work

    WORK IN PROGRESS NEXT WEEK (02/08/2026 - 02/14/2026):

    • Complete surcharge removal
    • Continue work on approach ramps
    • Complete utility installation under the bridge

    UPCOMING WORK THROUGH 02/28/2026:

    • Work will continue on new bridge substructure and bridge deck.
    • Utility work
    • Work on east and west approach ramps



    Removing cure blankets of concrete bridge deck


    Completed subgrade on west approach ramp




  • 01/30/2026 Construction Update

    WORK COMPLETED FOR WEEK ENDING 01/31/2026:

    • Continued utility installation under the bridge
    • Continued surcharge material removal
    • Continued approach ramp work

    WORK IN PROGRESS NEXT WEEK (02/01/2026 - 02/07/2026):

    • Complete surcharge material removal
    • Pour concrete approach ramps
    • Continued utility installation under the bridge

    UPCOMING WORK THROUGH 02/28/2026:

    • Work will continue on new bridge substructure and bridge deck.
    • Utility work
    • Work on east and west approach ramps



    Surcharge Material Removal at West Approach Ramp



Page last updated: 03 Apr 2026, 08:50 AM