11/25/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 11/28/2026:
- Continue installation of wall 1
- Install surcharge at wall 3
- Clear and grub behind wall 3
WORK IN PROGRESS NEXT WEEK (11/29/2026 - 12/05/2026):
- Continue installation of wall 1
- Backfill behind wingwall at wall 3 and complete surcharge
UPCOMING WORK THROUGH 11/30/2026:
- Build walls and pier caps
Installing Wall 1
Grading and Compacting Surcharge at Wall 3