11/25/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 11/28/2026:

  • Continue installation of wall 1
  • Install surcharge at wall 3
  • Clear and grub behind wall 3

WORK IN PROGRESS NEXT WEEK (11/29/2026 - 12/05/2026):

  • Continue installation of wall 1
  • Backfill behind wingwall at wall 3 and complete surcharge

UPCOMING WORK THROUGH 11/30/2026:

  • Build walls and pier caps


Installing Wall 1

Grading and Compacting Surcharge at Wall 3