10/23/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 10/24/2026:

  • Removed forms for pier 1 cap
  • Installed forms and rebar for pier 1 backwall
  • Stripped forms for pier 3 backwall
  • Continue installation of wall 1

WORK IN PROGRESS NEXT WEEK (10/25/2026 - 10/31/2026):

  • Continue subgrade for wall 3
  • Continue wall 3 drainage
  • Continue installation of wall 3

UPCOMING WORK THROUGH 10/31/2026:

  • Build walls and pier caps


Installing Rebar at Pier 1 Backwall


Placing Rock Armoring at Pier 3