10/23/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 10/24/2026:
- Removed forms for pier 1 cap
- Installed forms and rebar for pier 1 backwall
- Stripped forms for pier 3 backwall
- Continue installation of wall 1
WORK IN PROGRESS NEXT WEEK (10/25/2026 - 10/31/2026):
- Continue subgrade for wall 3
- Continue wall 3 drainage
- Continue installation of wall 3
UPCOMING WORK THROUGH 10/31/2026:
- Build walls and pier caps
Installing Rebar at Pier 1 Backwall
Placing Rock Armoring at Pier 3