09/11/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 09/12/2026:

  • Completed pier 1
  • Prepped for shaft tie-ins
  • Started painting columns

WORK IN PROGRESS NEXT WEEK (09/13/2026 - 09/19/2026):

  • Completed column tie-ins
  • Remove temporary work platforms
  • Remove remaining revetment panels

UPCOMING WORK THROUGH 09/30/2026:

  • In-water work window

Installing Column Rebar

Excavating Shaft 1- South