WORK COMPLETED FOR WEEK ENDING 11/07/2026:

  • Continue installation of wall 1
  • Continue installation of wall 3

WORK IN PROGRESS NEXT WEEK (11/08/2026 - 11/14/2026):

  • Continue installation of wall 1
  • Continue installation of wall 3

UPCOMING WORK THROUGH 11/30/2026:

  • Build walls and pier caps