11/20/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 11/21/2026:
- Continue installation of wall 1
- Continue installation of wall 3
- Installed pier 3 wingwall
WORK IN PROGRESS NEXT WEEK (11/22/2026 - 11/28/2026):
- Continue installation of wall 1
UPCOMING WORK THROUGH 11/30/2026:
- Build walls and pier caps
Placing Pier 3 Wingwall
Wall 3 Construction