10/16/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 10/17/2026:
- Place pier 1 cap
- Install forms and rebar for pier 3 backwall
- Place Pier 3 backwall
- Continue installation of wall 1
WORK IN PROGRESS NEXT WEEK (10/11/2026 - 10/17/2026):
- Continue subgrade for wall 3
- Install wall 3 drainage
- Start installation of wall 3
- Remove forms for pier 1 cap
- Form pier 1 backwall
- Strip forms for pier 3 backwall
UPCOMING WORK THROUGH 10/31/2026:
- Build walls and pier caps
Forms for Pier 1 Cap
Placing Back Wall at Pier 3