10/16/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 10/17/2026:

  • Place pier 1 cap
  • Install forms and rebar for pier 3 backwall
  • Place Pier 3 backwall
  • Continue installation of wall 1

WORK IN PROGRESS NEXT WEEK (10/11/2026 - 10/17/2026):

  • Continue subgrade for wall 3
  • Install wall 3 drainage
  • Start installation of wall 3
  • Remove forms for pier 1 cap
  • Form pier 1 backwall
  • Strip forms for pier 3 backwall

UPCOMING WORK THROUGH 10/31/2026:

  • Build walls and pier caps