09/17/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 09/19/2026:
- Completed column tie-ins
- Removed temporary work platforms
- Removed revetment panels
WORK IN PROGRESS NEXT WEEK (09/20/2026 - 09/26/2026):
- Form and pour cap at pier 3
- Install rebar for caps at pier 2 & 3
- Remove remaining work finger and reaction frame
UPCOMING WORK THROUGH 09/30/2026:
- In-water work window
Removing Temporary Sheet Pile
Painting Column 2 South