09/17/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 09/19/2026:

  • Completed column tie-ins
  • Removed temporary work platforms
  • Removed revetment panels

WORK IN PROGRESS NEXT WEEK (09/20/2026 - 09/26/2026):

  • Form and pour cap at pier 3
  • Install rebar for caps at pier 2 & 3
  • Remove remaining work finger and reaction frame

UPCOMING WORK THROUGH 09/30/2026:

  • In-water work window


Removing Temporary Sheet Pile

Painting Column 2 South