WORK COMPLETED FOR WEEK ENDING 10/31/2026:
- Poured pier 1 backwall
- Placed girder grout pads
- Continue installation of wall 3
WORK IN PROGRESS NEXT WEEK (11/01/2026 - 11/07/2026):
- Continue installation of wall 1
- Remove pier 1 backwall forms
- Continue installation of wall 3
UPCOMING WORK THROUGH 11/30/2026:
- Build walls and pier caps