10/09/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 10/10/2026:

  • Fish window ended on 9/30/2026 - all in-water work was completed.
  • Install forms and rebar at pier 1 cap
  • Place Pier 2 cap
  • Begin subgrade for wall 1

WORK IN PROGRESS NEXT WEEK (10/11/2026 - 10/17/2026):

  • Continue installation of wall 1
  • Begin subgrade for wall 3
  • Place rebar and close forms for pier 3 backwall
  • Place pier 1 cap
  • Strip pier 2 crosspiece forms


UPCOMING WORK THROUGH 10/31/2026:

  • Build walls and pier caps


Pier 2 Formwork

Pier 2 Cross Piece