10/09/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 10/10/2026:
- Fish window ended on 9/30/2026 - all in-water work was completed.
- Install forms and rebar at pier 1 cap
- Place Pier 2 cap
- Begin subgrade for wall 1
WORK IN PROGRESS NEXT WEEK (10/11/2026 - 10/17/2026):
- Continue installation of wall 1
- Begin subgrade for wall 3
- Place rebar and close forms for pier 3 backwall
- Place pier 1 cap
- Strip pier 2 crosspiece forms
UPCOMING WORK THROUGH 10/31/2026:
- Build walls and pier caps
Pier 2 Formwork
Pier 2 Cross Piece