Category Construction Update Show all
-
09/06/22 Construction Update
Work completed for Week Ending 09/02/2022:
- Kincaid Avenue (Maple to Main):
- Complete waterline installation on Kincaid north of Maple.
Work in progress this week (09/06/2022 - 09/09/2022):
- Kincaid Avenue (Main to Maple)
- Complete installation of joint utility trench
- Complete demolition
- Kincaid Avenue and Maple Street intersection:
- Complete waterline installation at intersection
- Kincaid Avenue (Academy to Maple):
- Begin waterline installation south of Maple Street.
Upcoming Work through 09/23/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue waterline installation south of Maple Street.
- Kincaid Avenue (Park to Academy)
- Begin waterline installation.
- Kincaid Avenue (Maple to Main):
-
08/30/22 Construction Update
Work completed for Week Ending 08/26/2022:
- Kincaid Avenue (Maple to Main):
- Complete demolition.
- Pothole for water
Work in progress this week (08/29/2022 - 09/02/2022):
- Kincaid Avenue (Maple to Main):
- Complete waterline installation on Kincaid north of Maple.
- Complete joint utility trench (JUT).
- Kincaid Avenue (Academy to Maple):
- Begin waterline installation south of Maple Street.
Upcoming Work through 09/16/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Intersection of Kincaid Avenue and Maple Street
- Tuesday (9/6) full intersection closure to complete waterline installation across Maple Street.
- Kincaid Avenue (Academy to Maple):
- Continue waterline installation south of Maple Street.
- Kincaid Avenue (Maple to Main):
-
08/22/22 Construction Update
Work completed for Week Ending 08/19/2022:
- Kincaid Avenue (Maple to Main):
- Clear and grub
- Storm drainage system installation
Work in progress this week (08/22/2022 - 08/26/2022):
- Kincaid Avenue (Maple to Main):
- Complete demolition.
- Pothole for water
- Begin waterline installation at Kincaid and Maple intersection
Upcoming Work through 09/09/2022:
- Kincaid Avenue (Maple to Main):
- Complete waterline installation at Kincaid and Maple intersection
- Begin joint utility trench (JUT)
- Begin illumination system
- Kincaid Avenue (Maple to Main):
-
08/15/22 Construction Update
All pedestrian access to businesses is delineated and maintained. Signs stating businesses open will be going out today near the intersection of Kincaid Avenue and Main Street.
Parking Update for the Town Center Utility Woonerf Project
In the public parking lot on the south side of Main between Kincaid & Alder, we’re going to have to close all the stalls on the south side of the lot (yellow). We realize parking is already tight with the loss of Kincaid and were hoping to keep half of these stalls open, the portion to the right. However, the alley/drive to the south of this area is private property without a public easement, and we were unable to secure access from the owner to route vehicles through there. All cars using the public lot will have to park on the north side only (green) and use the former south stalls to exit safely onto Alder Avenue. We apologize for the inconvenience.
Work completed for Week Ending 08/12/2022:
- Kincaid Avenue (Maple to Main): Set up traffic control
- Kincaid Avenue (Maple to Main): Set up erosion control
Work in progress this week (08/15/2022 - 08/19/2022):
- Kincaid Avenue (Maple to Main): Demolition
- Kincaid Avenue (Maple to Main): Clear and grub
- Kincaid Avenue (Maple to Main): Storm drainage system installation
Upcoming Work through 09/02/2022:
- Kincaid Avenue (Maple to Main): Water system installation
-
Preliminary Project Schedule
The Contractor’s current schedule for the Town Center: Utility & Woonerf project shows the following locations and approximate durations of work:
Kincaid Avenue (Main St to Maple St)
August 2022 – November 2022
Kincaid Avenue - water (Maple St to Park St)
mid-September 2022 – November 2022
Park Street - water (Kincaid Ave to Alder Ave)
November 2022
Academy Street - water (Kincaid Ave to Alder Ave)
November 2022
Alder Avenue - water (Maple St to Park St)
November 2022 – January 2023
Cherry Avenue (Main St to Maple St, including the intersection at Main St)
November 2022 – April 2023
Kincaid, Park, and Alder Concrete
January 2023 – February 2023
Academy Street Bike Lanes – paving (Narrow St to Wood Ave)
February 2023 – May 2023
In construction, schedules are rarely exact and will shift and adjust as the construction progresses – but this is where we are starting from and we will continue to update this as we proceed through this exciting project.
-
Notice to Proceed
The City issued Notice to Proceed (NTP) to the Contractor, Reed Trucking & Excavating, to begin construction on Monday, August 8th. The Contractor is starting work on Kincaid Avenue between Main Street and Maple Street. Pedestrian access to the businesses will be maintained, but the roadway will be closed to vehicles (including parking). The Contractor's first activities in August will be to set up traffic control and erosion control, clearing and grubbing, and demolition of the existing roadway to begin installation of the new storm drainage pipes and catch basins on the east side of Kincaid Avenue.
The plan below shows all of the work that needs to be done in this one little block on Kincaid Avenue.
-
Moving towards construction
This project has been awarded to Reed Excavating & Trucking to construct. The Pre-Construction meeting was held on 7/19/22 and construction is expected to start in early August.