08/22/22 Construction Update

Work completed for Week Ending 08/19/2022:

  • Kincaid Avenue (Maple to Main):
    • Clear and grub
    • Storm drainage system installation

08/17/22 Storm drainage installation on east side of Kincaid Avenue, north of Maple Street.
08/18/22 Compacting walkway after storm drainage installation on east side of Kincaid Avenue

08/19/22 Kincaid Avenue construction between Maple Street and Main Street

Work in progress this week (08/22/2022 - 08/26/2022):

  • Kincaid Avenue (Maple to Main):
    • Complete demolition.
    • Pothole for water
    • Begin waterline installation at Kincaid and Maple intersection

Upcoming Work through 09/09/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete waterline installation at Kincaid and Maple intersection
    • Begin joint utility trench (JUT)
    • Begin illumination system