09/06/22 Construction Update
Work completed for Week Ending 09/02/2022:
- Kincaid Avenue (Maple to Main):
- Complete waterline installation on Kincaid north of Maple.
Work in progress this week (09/06/2022 - 09/09/2022):
- Kincaid Avenue (Main to Maple)
- Complete installation of joint utility trench
- Complete demolition
- Kincaid Avenue and Maple Street intersection:
- Complete waterline installation at intersection
- Kincaid Avenue (Academy to Maple):
- Begin waterline installation south of Maple Street.
Upcoming Work through 09/23/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Kincaid Avenue (Academy to Maple):
- Continue waterline installation south of Maple Street.
- Kincaid Avenue (Park to Academy)
- Begin waterline installation.