Work completed for Week Ending 09/02/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete waterline installation on Kincaid north of Maple.

08/29/22: Installing conduits for joint utility trench (JUT) on Kincaid Avenue between Main Street and Maple Street

08/29/22: Kincaid Avenue looking north from Maple Street towards Main Street.

09/01/22: Excavating for waterline installation and connection on Maple Street east of Kincaid Avenue

Work in progress this week (09/06/2022 - 09/09/2022):

  • Kincaid Avenue (Main to Maple)
    • Complete installation of joint utility trench
    • Complete demolition
  • Kincaid Avenue and Maple Street intersection:
    • Complete waterline installation at intersection
  • Kincaid Avenue (Academy to Maple):
    • Begin waterline installation south of Maple Street.

Upcoming Work through 09/23/2022:

  • Kincaid Avenue (Maple to Main):
    • Begin illumination system.
    • Begin irrigation system.
  • Kincaid Avenue (Academy to Maple):
    • Continue waterline installation south of Maple Street.
  • Kincaid Avenue (Park to Academy)
    • Begin waterline installation.