08/15/22 Construction Update
All pedestrian access to businesses is delineated and maintained. Signs stating businesses open will be going out today near the intersection of Kincaid Avenue and Main Street.
Parking Update for the Town Center Utility Woonerf Project
In the public parking lot on the south side of Main between Kincaid & Alder, we’re going to have to close all the stalls on the south side of the lot (yellow). We realize parking is already tight with the loss of Kincaid and were hoping to keep half of these stalls open, the portion to the right. However, the alley/drive to the south of this area is private property without a public easement, and we were unable to secure access from the owner to route vehicles through there. All cars using the public lot will have to park on the north side only (green) and use the former south stalls to exit safely onto Alder Avenue. We apologize for the inconvenience.
Work completed for Week Ending 08/12/2022:
- Kincaid Avenue (Maple to Main): Set up traffic control
- Kincaid Avenue (Maple to Main): Set up erosion control
Work in progress this week (08/15/2022 - 08/19/2022):
- Kincaid Avenue (Maple to Main): Demolition
- Kincaid Avenue (Maple to Main): Clear and grub
- Kincaid Avenue (Maple to Main): Storm drainage system installation
Upcoming Work through 09/02/2022:
- Kincaid Avenue (Maple to Main): Water system installation