Preliminary Project Schedule

The Contractor’s current schedule for the Town Center: Utility & Woonerf project shows the following locations and approximate durations of work:

Kincaid Avenue (Main St to Maple St)
August 2022 – November 2022
Kincaid Avenue - water (Maple St to Park St)
mid-September 2022 – November 2022
Park Street - water (Kincaid Ave to Alder Ave)
November 2022
Academy Street - water (Kincaid Ave to Alder Ave)
November 2022
Alder Avenue - water (Maple St to Park St)
November 2022 – January 2023
Cherry Avenue (Main St to Maple St, including the intersection at Main St)
November 2022 – April 2023
Kincaid, Park, and Alder Concrete
January 2023 – February 2023
Academy Street Bike Lanes – paving (Narrow St to Wood Ave)
February 2023 – May 2023


In construction, schedules are rarely exact and will shift and adjust as the construction progresses – but this is where we are starting from and we will continue to update this as we proceed through this exciting project.