08/30/22 Construction Update
Work completed for Week Ending 08/26/2022:
- Kincaid Avenue (Maple to Main):
- Complete demolition.
- Pothole for water
Work in progress this week (08/29/2022 - 09/02/2022):
- Kincaid Avenue (Maple to Main):
- Complete waterline installation on Kincaid north of Maple.
- Complete joint utility trench (JUT).
- Kincaid Avenue (Academy to Maple):
- Begin waterline installation south of Maple Street.
Upcoming Work through 09/16/2022:
- Kincaid Avenue (Maple to Main):
- Begin illumination system.
- Begin irrigation system.
- Intersection of Kincaid Avenue and Maple Street
- Tuesday (9/6) full intersection closure to complete waterline installation across Maple Street.
- Kincaid Avenue (Academy to Maple):
- Continue waterline installation south of Maple Street.