08/30/22 Construction Update

Work completed for Week Ending 08/26/2022:

  • Kincaid Avenue (Maple to Main):
    • Complete demolition.
    • Pothole for water

08/22/22 Sawcutting on Maple Street east of Kincaid Avenue 08/22/22 Asphalt demolition on Maple Street east of Kincaid Avenue 08/24/22 Installing new 8" ductile iron water pipe on Kincaid Avenue north of Maple Street 08/24/22 Compacting water backfill on Kincaid Avenue north of Maple Street


08/25/22 Installing 8"x8" water cross at the intersection of Kincaid Avenue and Maple Street

Work in progress this week (08/29/2022 - 09/02/2022):

  • Kincaid Avenue (Maple to Main):
    • Complete waterline installation on Kincaid north of Maple.
    • Complete joint utility trench (JUT).
  • Kincaid Avenue (Academy to Maple):
    • Begin waterline installation south of Maple Street.

Upcoming Work through 09/16/2022:

  • Kincaid Avenue (Maple to Main):
    • Begin illumination system.
    • Begin irrigation system.
  • Intersection of Kincaid Avenue and Maple Street
    • Tuesday (9/6) full intersection closure to complete waterline installation across Maple Street.
  • Kincaid Avenue (Academy to Maple):
    • Continue waterline installation south of Maple Street.
Categories: Construction Update