• 5/01/2025 CONSTRUCTION UPDATE

    WORK COMPLETED FOR WEEK ENDING 04/25/2025:

    • Erosion Control Installation
    • Demolition work in Heritage Park
    • Demotion Work in Hops Alley
    • Pothole Utilities

    WORK IN PROGRESS THIS WEEK (04/21/2025 - 04/25/2025):

    • Erosion Control Installation Complete
    • Demolition Work in Heritage Park
    • Demotion Work in Hops Alley
    • Pothole Utilities
    • Water Line Locates

    UPCOMING WORK THROUGH 05/16/2025:

    • Water Main in Hops Alley
    • Deep Pole Foundation Work for Overhead Lighting System in Hops Alley


  • 4/23/2025 CONSTRUCTION UPDATE

    WORK COMPLETED FOR WEEK ENDING 04/18/2025:

    • Contractor mobilized onsite
    • Completed Survey & Locates

    WORK IN PROGRESS THIS WEEK (04/21/2025 - 04/25/2025):

    • Erosion Control Installation
    • Demolition work in Heritage Park
    • Demotion Work in Hops Alley
    • Pothole for Utilities

    UPCOMING WORK THROUGH 05/02/2025:

    • Erosion Control Installation
    • Demolition Work in Heritage Park
    • Demotion Work in Hops Alley
    • Pothole Utilities