-
5/29/2025 CONSTRUCTION UPDATE
WORK COMPLETED FOR WEEK ENDING 05/30/2025:
5/27/2025 - KINCAID CLOSURE
- Pressure Test Water Main & Purity Test
- Sawcut and Demo Concrete on Kincaid
- Install Sewer manhole on Kincaid
- Watermain tie in on Kincaid
- Hops Alley Sewer install
WORK IN PROGRESS NEXT WEEK (06/02/2025 - 06/06/2025)
**06/04/2025 ALDER AVE NIGHT WORK - Sawcut, Demo and install waterline in Alder
- Hops Alley Sewer install
- Deep Pole Foundation Work for Overhead Lighting System in Heritage Park
UPCOMING WORK THROUGH 06/30/2025
**KINCAID CLOSURE - Tentatively from 6/13/2025 to 6/25/2025 to grade, install rebar, and pour back concrete
- Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
- Silva Cell System install in Hops Alley
- Stormwater install in Hops Alley
We realize the impacts of a road closure and are working with the contractor to see if this window can be shortened at all. We’re also trying to see if there’s an option to make the temporary dumpster situation easier during the closure. We can’t make any promises, but keep watching these updates for more information. Next week, we will be adding a banner to the fence at Heritage Park, encouraging customers to shop and eat in Sumner, assuring the public that you all are open with great options to enjoy through construction.
Installation of new Sewer Manhole in Kincaid Ave
-
5/22/2025 CONSTRUCTION UPDATE
WORK COMPLETED FOR WEEK ENDING 05/16/2025:
- Civil Underground Demolition and Excavation
- Pothole Utilities
- Water Main excavation in Hops Alley
WORK IN PROGRESS NEXT WEEK (05/27/2025 - 05/30/2025):
**5/27/2025 - KINCAID AVE CLOSURE starting at 7:00am**
**5/30/2025 - Kincaid Ave Open**
- Pressure Test Water Main & Purity Test
- Sawcut and Demo Concrete on Kincaid Ave
- Install Sewer manhole on Kincaid Ave
- Watermain tie in on Kincaid Ave
- Hops Alley Sewer install
UPCOMING WORK THROUGH 06/13/2025:
- Sawcut, Demo and install waterline in Alder Ave
- Deep Pole Foundation Work for Overhead Lighting System in Heritage Park & Hops Alley
-
5/14/2025 CONSTRUCTION UPDATE
WORK COMPLETED FOR WEEK ENDING 05/09/2025:
- Demolition Work in Heritage Park
- Demotion Work in Hops Alley
- Pothole Utilities
- Water Line Locates
WORK IN PROGRESS THIS WEEK (05/12/2025 - 05/16/2025):
- Civil Underground Demolition and Excavation
- Pothole Utilities
- Water Main excavation in Hops Alley
UPCOMING WORK THROUGH 05/31/2025:
- Water Main install in Hops Alley (includes connection in Kincaid Ave & Alder Ave)
- Sewer Main in Hops Alley (Includes connection in Kincaid Ave)
- Deep Pole Foundation Work for Overhead Lighting System in Heritage Park
-
5/01/2025 CONSTRUCTION UPDATE
WORK COMPLETED FOR WEEK ENDING 04/25/2025:
- Erosion Control Installation
- Demolition work in Heritage Park
- Demotion Work in Hops Alley
- Pothole Utilities
WORK IN PROGRESS THIS WEEK (04/21/2025 - 04/25/2025):
- Erosion Control Installation Complete
- Demolition Work in Heritage Park
- Demotion Work in Hops Alley
- Pothole Utilities
- Water Line Locates
UPCOMING WORK THROUGH 05/16/2025:
- Water Main in Hops Alley
- Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
-
4/23/2025 CONSTRUCTION UPDATE
WORK COMPLETED FOR WEEK ENDING 04/18/2025:
- Contractor mobilized onsite
- Completed Survey & Locates
WORK IN PROGRESS THIS WEEK (04/21/2025 - 04/25/2025):
- Erosion Control Installation
- Demolition work in Heritage Park
- Demotion Work in Hops Alley
- Pothole for Utilities
UPCOMING WORK THROUGH 05/02/2025:
- Erosion Control Installation
- Demolition Work in Heritage Park
- Demotion Work in Hops Alley
- Pothole Utilities