08/28/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/29/2025:
- Restored north sidewalk in Hops Alley
- Performed underground electrical work in Hops Alley.
WORK IN PROGRESS NEXT WEEK (09/01/2025 - 09/05/2025):
- Stormwater work in Heritage Park
- Install electrical components within the Heritage Park seat wall
- Pour concrete for Heritage Park seat wall
- Perform underground electrical work in Heritage Park and Hops Alley
- Start forming for trash enclosure in Hops Alley
UPCOMING WORK THROUGH 09/30/2025:
- Connect Hops Alley to water main in Alder Ave - tentatively work will begin on 9/8/2025
- Install metal planter beds in Heritage Park and Hops Alley
- Install irrigation system in Hops Alley
- Concrete paving and curb construction in Hops Alley
Fresh concrete poured and curing for the north sidewalk.
-
08/21/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/21/2025:
- Performed underground electrical work in Hops Alley
- Installed Silva Cell systems in Hops Alley
- Installed water services in Hops Alley
WORK IN PROGRESS NEXT WEEK (08/25/2025 - 08/29/2025):
- Restore north sidewalk in Hops Alley (scheduled for 8/27–8/28)
- Stormwater work in Heritage Park
- Install electrical components within the Heritage Park seat wall
- Pour concrete for Heritage Park seat wall
UPCOMING WORK THROUGH 09/30/2025:
- Perform underground electrical work in Heritage Park
- Connect Hops Alley to water main in Alder Ave
- Install metal planter beds in Heritage Park and Hops Alley
- Install irrigation system in Hops Alley
North sidewalk concrete pour plan
Underground electrical work in Hops Alley
Underground electrical work in Hops Alley
-
08/14/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/15/2025:
- Set forms and installed additional rebar for the Heritage Park seat wall
- Stormwater improvements in Hops Alley
- Installed Silva Cell systems in Hops Alley
- Installed irrigation sleeves in Hops Alley
- Installed water services in Hops Alley
WORK IN PROGRESS NEXT WEEK (08/18/2025 - 08/22/2025):
- Pour concrete for Heritage Park seat wall
- Stormwater work in Heritage Park
- Install Silva Cell systems in Hops Alley
- Install electrical components within the Heritage Park seat wall
- Perform underground electrical work in Hops Alley
UPCOMING WORK THROUGH 08/29/2025:
- Perform underground electrical work in Heritage Park
- Restore north sidewalk in Hops Alley (scheduled for 8/27–8/28)
North sidewalk concrete pour plan
Installation of water services in Hops Alley
Trenching in Hops Alley
-
08/07/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/08/2025:
- Set forms and installed additional rebar for the Heritage Park seat wall
- Completed stormwater improvements in Hops Alley
- Installed Silva Cell system in Hops Alley
- Installed irrigation sleeves in Hops Alley
WORK IN PROGRESS NEXT WEEK (08/11/2025 - 08/15/2025):
- Pour concrete for Heritage Park seat wall
- Stormwater work in Heritage Park
- Install additional Silva Cell systems in Hops Alley
- Install additional irrigation sleeves in Hops Alley
- Install electrical components within the Heritage Park seat wall
UPCOMING WORK THROUGH 08/29/2025:
- Install Water Services in Hops Alley
- Perform underground electrical work in both Hops Alley and Heritage Park
- Restore north sidewalk in Hops Alley (scheduled for 8/27–8/28)
North sidewalk concrete pour plan
Final improvements to Hops Alley stormwater system
Rebar and Forms for the Heritage Park seat wall
-
07/31/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/31/2025:
**KINCAID CLOSURE – July 16–28 (Road reopened Monday morning, July 28)
- Set forms and installed additional rebar for the Heritage Park seat wall
- Continued stormwater improvements in Hops Alley
WORK IN PROGRESS NEXT WEEK (08/04/2025 - 08/08/2025):
- Set forms and install rebar for the concrete seat wall in Heritage Park
- Install electrical components within the Heritage Park seat wall
- Ongoing stormwater work in Hops Alley and Heritage Park
- Install Silva Cell system in Hops Alley
- Install irrigation sleeves in Hops Alley
UPCOMING WORK THROUGH 08/29/2025:
- Install Water Services in Hops Alley
- Perform underground electrical work in both Hops Alley and Heritage Park
- Pour concrete for the Heritage Park seat wall
Rebar and forms for the concrete seat wall in Heritage Park
Roadway Restoration Completed on Kincaid Street
-
07/24/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/25/2025:
- Poured footings and installed additional rebar for the Heritage Park seat wall
- Stormwater work in Hops Alley
- Poured concrete to restore the roadway surface on Kincaid Street
WORK IN PROGRESS NEXT WEEK (07/28/2025 - 08/01/2025):
**KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Ongoing stormwater work in Hops Alley and Heritage Park
- Set forms and install rebar for the concrete seat wall in Heritage Park
- Pour Concrete footing for seat wall in Heritage Park
UPCOMING WORK THROUGH 08/28/2025:
- Install Water Services in Hops Alley
- Install Silva Cell system in Hops Alley
- Perform underground electrical work in both Hops Alley and Heritage Park
- Install electrical components within the Heritage Park seat wall
- Pour concrete for the Heritage Park seat wall
Concrete pour underway on Kincaid Street as crews restore roadway surface following underground utility work.
Foundation completed for concrete seat wall in Heritage Park
-
07/17/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/18/2025:
- Set forms and installed rebar for the concrete seat wall in Heritage Park
- Stormwater work in Hops Alley
- Installed bollard sockets in Hops Alley
WORK IN PROGRESS NEXT WEEK (07/21/2025 - 07/25/2025):
**KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Pour concrete to restore the roadway surface on Kincaid Street
- Pour footings and install additional rebar for the Heritage Park seat wall
- Ongoing stormwater work in Hops Alley
UPCOMING WORK THROUGH 08/28/2025:
- Install Water Services in Hops Alley
- Install Silva Cell system in Hops Alley
- Perform underground electrical work in both Hops Alley and Heritage Park
- Install electrical components within the Heritage Park seat wall
- Pour concrete for the Heritage Park seat wall
Stormwater work in Hops Alley
Forms and Rebar for Concrete seat wall in Heritage Park
-
07/10/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/11/2025:
- Set forms and installed rebar for the concrete seat wall in Heritage Park
- Stormwater work in Hops Alley
WORK IN PROGRESS NEXT WEEK (07/14/2025 - 07/18/2025):
- Pour footings, and install additional rebar for the concrete seat wall in Heritage Park
- Begin installation of electrical equipment within the seat wall
- Ongoing stormwater work in Hops Alley
- Install Silva Cell system in Hops Alley
- Install bollard sockets in Hops Alley
UPCOMING WORK THROUGH 07/25/2025:
**KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Install Water Services in Hops Alley
- Pour concrete for the Heritage Park seat wall
- Stormwater work in Heritage Park
Forms and Rebar for Concrete seat wall in Heritage Park
Stormwater Work in Hops Alley
-
7/3/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/04/2025:
- Excavated footings and installed rebar for the concrete seat wall in Heritage Park
- Stormwater work in Hops Alley
WORK IN PROGRESS NEXT WEEK (07/07/2025 - 07/11/2025):
- Set forms, pour footings, and install rebar for the concrete seat wall in Heritage Park
- Ongoing stormwater work in Hops Alley
UPCOMING WORK THROUGH 07/25/2025:
**KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Install Water Services in Hops Alley
- Install bollard foundations in Hops Alley
- Pour concrete for the Heritage Park seat wall
- Install Silva Cell system in Hops Alley
- Stormwater work in Heritage Park
Stormwater pipe installation in Hops Alley
-
6/26/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 06/27/2025:
- Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
- Survey and dig footings for Concrete Seat wall in Heritage Park
- Dig, Form and Pour Concrete for Umbrella foundations in Heritage Park
WORK IN PROGRESS NEXT WEEK (06/30/2025 - 07/4/2025):
- Begin installation of Silva Cell System in Hops Alley
- Excavate footings, set forms, and install rebar for the concrete seat wall in Heritage Park
- Begin Stormwater work in Hops Alley & Heritage Park
UPCOMING WORK THROUGH 07/25/2025:
**KINCAID CLOSURE - Postponed to after Rhubarb Day, tentatively planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Install Water Services in Hops Alley
- Install bollard foundations in Hops Alley
- Pour concrete for the Heritage Park seat wall
Digging footings for Concrete Seat wall in Heritage Park
Concrete Pour for Pole Foundations in Hops Alley