• 07/10/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 07/11/2025:

    • Set forms and installed rebar for the concrete seat wall in Heritage Park
    • Stormwater work in Hops Alley

    WORK IN PROGRESS NEXT WEEK (07/14/2025 - 07/18/2025):

    • Pour footings, and install additional rebar for the concrete seat wall in Heritage Park
    • Begin installation of electrical equipment within the seat wall
    • Ongoing stormwater work in Hops Alley
    • Install Silva Cell system in Hops Alley
    • Install bollard sockets in Hops Alley

    UPCOMING WORK THROUGH 07/25/2025:

    **KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)

    • Install Water Services in Hops Alley
    • Pour concrete for the Heritage Park seat wall
    • Stormwater work in Heritage Park Forms and Rebar for Concrete seat wall in Heritage Park
      Stormwater Work in Hops Alley

  • 7/3/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 07/04/2025:

    • Excavated footings and installed rebar for the concrete seat wall in Heritage Park
    • Stormwater work in Hops Alley

    WORK IN PROGRESS NEXT WEEK (07/07/2025 - 07/11/2025):

    • Set forms, pour footings, and install rebar for the concrete seat wall in Heritage Park
    • Ongoing stormwater work in Hops Alley

    UPCOMING WORK THROUGH 07/25/2025:

    **KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)

    • Install Water Services in Hops Alley
    • Install bollard foundations in Hops Alley
    • Pour concrete for the Heritage Park seat wall
    • Install Silva Cell system in Hops Alley
    • Stormwater work in Heritage Park

    Stormwater pipe installation in Hops Alley


  • 6/26/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 06/27/2025:

    • Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
    • Survey and dig footings for Concrete Seat wall in Heritage Park
    • Dig, Form and Pour Concrete for Umbrella foundations in Heritage Park

    WORK IN PROGRESS NEXT WEEK (06/30/2025 - 07/4/2025):

    • Begin installation of Silva Cell System in Hops Alley
    • Excavate footings, set forms, and install rebar for the concrete seat wall in Heritage Park
    • Begin Stormwater work in Hops Alley & Heritage Park

    UPCOMING WORK THROUGH 07/25/2025:

    **KINCAID CLOSURE - Postponed to after Rhubarb Day, tentatively planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)

    • Install Water Services in Hops Alley
    • Install bollard foundations in Hops Alley
    • Pour concrete for the Heritage Park seat wall


    Digging footings for Concrete Seat wall in Heritage Park

    Concrete Pour for Pole Foundations in Hops Alley




  • 6/18/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 06/20/2025:

    • Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
    • Begin Survey and dig footings for Concrete Seat wall in Heritage Park

    WORK IN PROGRESS NEXT WEEK (06/23/2025 - 06/27/2025):

    • Complete Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
    • Begin installation of Silva Cell System in Hops Alley
    • Footings, form, rebar, and pour concrete for Concrete Seat wall in Heritage Park

    UPCOMING WORK THROUGH 07/25/2025:

    **KINCAID CLOSURE - Postponed to after Rhubarb Day, tentatively planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)

    • Begin Stormwater work in Hops Alley & Heritage Park
    • Install Water Services in Hops Alley
    • Dig, Form and Pour Concrete for Umbrella foundations in Heritage Park

    Deep Foundations for Overhead Lighting in Hops Alley

  • 6/13/2025 CONSTRUCTION UPDATE

    WORK COMPLETED FOR WEEK ENDING 06/06/2025:

    • Hops Alley Sewer Install
    • Start Deep Pole Foundation Work for Overhead Lighting System in Heritage Park

    WORK IN PROGRESS NEXT WEEK (06/09/2025 - 06/13/2025):

    • Start Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
    • Complete Hops Alley Sewer install
    • Complete Deep Pole Foundation Work for Overhead Lighting System in Heritage Park

    UPCOMING WORK THROUGH 07/04/2025:

    • KINCAID CLOSURE - Postponed to after Rhubarb Days
    • Grade, install rebar and pour concrete
    • Silva Cell System install in Hops Alley
    • Stormwater install in Hops Alley
    • Survey, Footings, form, rebar, and pour concrete for Concrete Seat wall in Heritage Park

    Deep Pole Foundations in Heritage Park for New Overhead Lighting System

    Getting ready for new Sewer in Hops Alley

  • 5/29/2025 CONSTRUCTION UPDATE

    WORK COMPLETED FOR WEEK ENDING 05/30/2025:

    5/27/2025 - KINCAID CLOSURE

    • Pressure Test Water Main & Purity Test
    • Sawcut and Demo Concrete on Kincaid
    • Install Sewer manhole on Kincaid
    • Watermain tie in on Kincaid
    • Hops Alley Sewer install


    WORK IN PROGRESS NEXT WEEK (06/02/2025 - 06/06/2025)

    **06/04/2025 ALDER AVE NIGHT WORK - Sawcut, Demo and install waterline in Alder

    • Hops Alley Sewer install
    • Deep Pole Foundation Work for Overhead Lighting System in Heritage Park


    UPCOMING WORK THROUGH 06/30/2025

    **KINCAID CLOSURE - Tentatively from 6/13/2025 to 6/25/2025 to grade, install rebar, and pour back concrete

    • Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
    • Silva Cell System install in Hops Alley
    • Stormwater install in Hops Alley


    We realize the impacts of a road closure and are working with the contractor to see if this window can be shortened at all. We’re also trying to see if there’s an option to make the temporary dumpster situation easier during the closure. We can’t make any promises, but keep watching these updates for more information. Next week, we will be adding a banner to the fence at Heritage Park, encouraging customers to shop and eat in Sumner, assuring the public that you all are open with great options to enjoy through construction.


    Installation of new Sewer Manhole in Kincaid Ave



  • 5/22/2025 CONSTRUCTION UPDATE

    WORK COMPLETED FOR WEEK ENDING 05/16/2025:

    • Civil Underground Demolition and Excavation
    • Pothole Utilities
    • Water Main excavation in Hops Alley


    WORK IN PROGRESS NEXT WEEK (05/27/2025 - 05/30/2025):

    **5/27/2025 - KINCAID AVE CLOSURE starting at 7:00am**

    **5/30/2025 - Kincaid Ave Open**

    • Pressure Test Water Main & Purity Test
    • Sawcut and Demo Concrete on Kincaid Ave
    • Install Sewer manhole on Kincaid Ave
    • Watermain tie in on Kincaid Ave
    • Hops Alley Sewer install


    UPCOMING WORK THROUGH 06/13/2025:

    • Sawcut, Demo and install waterline in Alder Ave
    • Deep Pole Foundation Work for Overhead Lighting System in Heritage Park & Hops Alley
  • 5/14/2025 CONSTRUCTION UPDATE

    WORK COMPLETED FOR WEEK ENDING 05/09/2025:

    • Demolition Work in Heritage Park
    • Demotion Work in Hops Alley
    • Pothole Utilities
    • Water Line Locates

    WORK IN PROGRESS THIS WEEK (05/12/2025 - 05/16/2025):

    • Civil Underground Demolition and Excavation
    • Pothole Utilities
    • Water Main excavation in Hops Alley

    UPCOMING WORK THROUGH 05/31/2025:

    • Water Main install in Hops Alley (includes connection in Kincaid Ave & Alder Ave)
    • Sewer Main in Hops Alley (Includes connection in Kincaid Ave)
    • Deep Pole Foundation Work for Overhead Lighting System in Heritage Park


  • 5/01/2025 CONSTRUCTION UPDATE

    WORK COMPLETED FOR WEEK ENDING 04/25/2025:

    • Erosion Control Installation
    • Demolition work in Heritage Park
    • Demotion Work in Hops Alley
    • Pothole Utilities

    WORK IN PROGRESS THIS WEEK (04/21/2025 - 04/25/2025):

    • Erosion Control Installation Complete
    • Demolition Work in Heritage Park
    • Demotion Work in Hops Alley
    • Pothole Utilities
    • Water Line Locates

    UPCOMING WORK THROUGH 05/16/2025:

    • Water Main in Hops Alley
    • Deep Pole Foundation Work for Overhead Lighting System in Hops Alley


  • 4/23/2025 CONSTRUCTION UPDATE

    WORK COMPLETED FOR WEEK ENDING 04/18/2025:

    • Contractor mobilized onsite
    • Completed Survey & Locates

    WORK IN PROGRESS THIS WEEK (04/21/2025 - 04/25/2025):

    • Erosion Control Installation
    • Demolition work in Heritage Park
    • Demotion Work in Hops Alley
    • Pothole for Utilities

    UPCOMING WORK THROUGH 05/02/2025:

    • Erosion Control Installation
    • Demolition Work in Heritage Park
    • Demotion Work in Hops Alley
    • Pothole Utilities