• 12/30/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 12/26/2025:

    • Install trench Drain for Heritage Park
    • Install Hops Trellis in Hops Alley
    • Remove underground UST in Heritage Park
    • Install power bollards in Heritage Park & Hops Alley
    • Start install of power bollards in Heritage Park & Hops Alley

    WORK IN PROGRESS THIS WEEK (12/29/2025 - 1/02/2026):

    • Complete install of Hops Alley Entry sign
    • Complete install of Hops Alley Trash Enclosure gates
    • Complete Paver installation in Hops Alley
    • Complete install of Hops Trellis in Hops Alley
    • Complete Cable Fence & Timber Bench install in Hops Alley & Heritage Park

    UPCOMING WORK THROUGH 1/31/2026:

    • Timber Bench install in Heritage Park
    • Landscaping & tree install in Heritage Park
    • Overhead lighting install in Hops Alley & Heritage Park
    • Sumner Entry sign in Heritage Park



  • 12/18/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 12/12/2025:

    • Install trench Drain for Heritage Park
    • Install Light Poles in Heritage Park & Hops Alley
    • Install Hops Trellis in Hops Alley
    • Start install of power bollards in Heritage Park & Hops Alley

    WORK IN PROGRESS THIS WEEK (12/15/2025 - 12/19/2025):

    • Paver installation in Hops Alley
    • Install power bollards in Heritage Park & Hops Alley
    • Landscaping in Heritage Park
    • Complete install of Hops Trellis in Hops Alley

    UPCOMING WORK THROUGH 12/31/2025:

    • Install trash enclosure doors
    • Complete Paver installation in Hops Alley
    • Install Hops Alley Entry Sign
    • Cable Fence & Timber Bench install in Hops Alley & Heritage Park
    • Overhead lighting install in Hops Alley

    Pole Installation in Hops Alley

    Paver Installation in Hops Alley


  • 11/20/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 11/14/2025:

    • Prep and pour Alder driveway approach & sidewalk
    • Continue Landscaping in Hops Alley
    • Prep & pour concrete pavement in the park
    • Continue Irrigation in Heritage Park & Hops Alley

    WORK IN PROGRESS THIS WEEK (11/17/2025 - 11/21/2025):

    • Prep & pour concrete pavement in the park
    • Start Paver installation in Hops Alley
    • Asphalt striping in Hops Alley

    UPCOMING WORK THROUGH 12/12/2025:

    • Install trash enclosure panels
    • Install Entry Sign in Heritage Park
    • Install Hops Alley Entry Sign
    • Irrigation in Hops Alley & Heritage Park
    • Landscaping in Hops Alley
    • Cable Fence & Paver Installation in Hops Alley

    **ESTIMATED KINCAID AVE CLOSURE (1 Day week of 12/8/2025)


    Concrete Pour in Heritage Park

    Hops Alley Asphalt Striping

  • 11/13/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 11/07/2025:

    • Irrigation in Hops Alley
    • Landscaping in Hops Alley
    • Prep & pour concrete pavement in the park

    WORK IN PROGRESS THIS WEEK (11/10/2025 - 11/14/2025):

    • Prep and pour Alder driveway approach & sidewalk
    • Continue Landscaping in Hops Alley
    • Prep & pour concrete pavement in the park
    • Continue Irrigation in Heritage Park & Hops Alley

    UPCOMING WORK THROUGH 12/05/2025:

    • Concrete Paving in Heritage Park
    • Install trash enclosure panels
    • Install Entry Sign in Heritage Park
    • Irrigation in Hops Alley & Heritage Park
    • Landscaping in Hops Alley
    • Cable Fence & Paver Installation in Hops Alley
    • Installation of Entry Sign in Heritage Park

    Heritage Park Concrete

    Alder Driveway approach & Sidewalk

  • 11/5/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 10/31/2025:

    • Underground electrical work in Heritage Park
    • Irrigation in Hops Alley
    • Landscaping in Hops Alley
    • Install & waterproof metal planters in Heritage Park
    • Prep for installation of Entry Sign in Heritage Park

    WORK IN PROGRESS THIS WEEK (11/03/2025 - 11/07/2025):

    • Continue Landscaping in Hops Alley
    • Continue Prep for installation of Entry Sign in Heritage Park
    • Prep for concrete pavement in the park
    • Continue Irrigation in Heritage Park & Hops Alley

    UPCOMING WORK THROUGH 11/30/2025:

    • Concrete Paving in Heritage Park & Hops Alley
    • Install Entry Sign in Heritage Park
    • Irrigation in Hops Alley & Heritage Park
    • Landscaping in Hops Alley
    • Cable Fence & Paver Installation in Hops Alley


    Foundation for New Park Entry Sign




    Tree installation in Hops Alley



  • 10/29/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 10/24/2025:

    • Underground electrical work in Heritage Park
    • Concrete in Hops Alley
    • Irrigation in Hops Alley

    WORK IN PROGRESS THIS WEEK (10/27/2025 - 10/31/2025):

    • Underground electrical work in Heritage Park
    • Irrigation in Hops Alley
    • Landscaping in Hops Alley
    • Install & waterproof metal planters in Heritage Park
    • Prep for installation of Entry Sign in Heritage Park

    UPCOMING WORK THROUGH 11/21/2025:

    • Concrete Paving in Heritage Park & Hops Alley
    • Install Entry Sign in Heritage Park
    • Irrigation in Hops Alley & Heritage Park
    • Landscaping in Hops Alley
    • Cable Fence & Paver Installation in Hops Alley


    Metal Planters in Heritage Park

    Irrigation Installation in Hops Alley

  • 10/22/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 10/17/2025:

    • Electrical Underground work in Heritage Park
    • Grading & Asphalt Paving in Hops Alley
    • Electrical Work in Hops Alley
    • Metal Planter bed installation in Hops Alley

    WORK IN PROGRESS NEXT WEEK (10/20/2025 - 10/24/2025):

    • Underground electrical work in Heritage Park
    • Concrete in Hops Alley
    • Irrigation in Hops Alley

    UPCOMING WORK THROUGH 11/14/2025:

    • Install metal planter beds in Heritage Park
    • Concrete in Heritage Park
    • Install Entry Sign Heritage Park
    • Irrigation in Hops Alley & Heritage Park
    • Landscaping in Hops Alley
    • Cable Fence & Paver Installation in Hops Alley

    Planter installation and Concrete & Asphalt in Hops Alley

    Underground Electrical installation in Heritage Park

  • 10/16/2025 Construction Update

    WORK COMPLETED

    Last week the contractor completed electrical and concrete curbs in the alley.

    WORK THIS WEEK

    • This week they are working towards the asphalt paving in the alley on Friday morning.
    • The paving will go from Alder Ave toward Kincaid Ave.
    • The contract knows the Homecoming Parade is happening at 4:30 in the afternoon and will work accordingly to not impact the parade.
    • Contractor crews will stage their equipment to the City Hall parking lot to minimize impact to the roads.

    WORK COMING UP

    Next week they will start on irrigation in both the parka and alley and work on more concrete in the alley.



  • 09/19/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 09/19/2025:

    • Stormwater work in Heritage Park
    • Poured concrete footings for trash enclosure in Hops Alley
    • Complete Water Service connections in Hops Alley and Heritage Park
    • Asphalt patching in Alder Ave

    WORK IN PROGRESS NEXT WEEK (09/22/2025 - 09/26/2025):

    • Perform underground electrical work in Heritage Park
    • Install metal planter beds in Hops Alley
    • Trash enclosure wall concrete pour in Hops Alley
    • Concrete paving and curb installation in Hops Alley

    UPCOMING WORK THROUGH 09/30/2025:

    • Install metal planter beds in Heritage Park and Hops Alley
    • Install irrigation sleeves in Heritage Park
    • Install irrigation system in Heritage Park
    • Asphalt paving in Hops Alley


    Asphalt patching in Alder Ave


    Forming for Hops Alley trash enclosure



  • 09/12/2025 Construction Update

    WORK COMPLETED FOR WEEK ENDING 09/12/2025:

    • Performed underground electrical work in Heritage Park
    • Connected Hops Alley to water main in Alder Ave
    • Start Stormwater work in Heritage Park
    • Set forms for trash enclosure in Hops Alley

    WORK IN PROGRESS NEXT WEEK (09/15/2025 - 09/19/2025):

    **Alder Ave will have roadwork occurring with traffic control to complete road restoration until 9/30

    • Perform underground electrical work in Heritage Park
    • Continue Stormwater work in Heritage Park
    • Pour concrete footings for trash enclosure in Hops Alley
    • Install irrigation sleeves in Hops Alley
    • Complete Water Service connections in Hops Alley

    UPCOMING WORK THROUGH 09/30/2025:

    • Install metal planter beds in Heritage Park and Hops Alley
    • Install irrigation system in Hops Alley
    • Concrete paving and curb construction in Hops Alley
    • Asphalt paving in Hops Alley


    Connecting Hops Alley to water main in Alder Ave