11/20/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 11/14/2025:

  • Prep and pour Alder driveway approach & sidewalk
  • Continue Landscaping in Hops Alley
  • Prep & pour concrete pavement in the park
  • Continue Irrigation in Heritage Park & Hops Alley

WORK IN PROGRESS THIS WEEK (11/17/2025 - 11/21/2025):

  • Prep & pour concrete pavement in the park
  • Start Paver installation in Hops Alley
  • Asphalt striping in Hops Alley

UPCOMING WORK THROUGH 12/12/2025:

  • Install trash enclosure panels
  • Install Entry Sign in Heritage Park
  • Install Hops Alley Entry Sign
  • Irrigation in Hops Alley & Heritage Park
  • Landscaping in Hops Alley
  • Cable Fence & Paver Installation in Hops Alley

**ESTIMATED KINCAID AVE CLOSURE (1 Day week of 12/8/2025)


Concrete Pour in Heritage Park

Hops Alley Asphalt Striping