09/19/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 09/19/2025:

  • Stormwater work in Heritage Park
  • Poured concrete footings for trash enclosure in Hops Alley
  • Complete Water Service connections in Hops Alley and Heritage Park
  • Asphalt patching in Alder Ave

WORK IN PROGRESS NEXT WEEK (09/22/2025 - 09/26/2025):

  • Perform underground electrical work in Heritage Park
  • Install metal planter beds in Hops Alley
  • Trash enclosure wall concrete pour in Hops Alley
  • Concrete paving and curb installation in Hops Alley

UPCOMING WORK THROUGH 09/30/2025:

  • Install metal planter beds in Heritage Park and Hops Alley
  • Install irrigation sleeves in Heritage Park
  • Install irrigation system in Heritage Park
  • Asphalt paving in Hops Alley


Asphalt patching in Alder Ave


Forming for Hops Alley trash enclosure