09/19/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 09/19/2025:
- Stormwater work in Heritage Park
- Poured concrete footings for trash enclosure in Hops Alley
- Complete Water Service connections in Hops Alley and Heritage Park
- Asphalt patching in Alder Ave
WORK IN PROGRESS NEXT WEEK (09/22/2025 - 09/26/2025):
- Perform underground electrical work in Heritage Park
- Install metal planter beds in Hops Alley
- Trash enclosure wall concrete pour in Hops Alley
- Concrete paving and curb installation in Hops Alley
UPCOMING WORK THROUGH 09/30/2025:
- Install metal planter beds in Heritage Park and Hops Alley
- Install irrigation sleeves in Heritage Park
- Install irrigation system in Heritage Park
- Asphalt paving in Hops Alley
Asphalt patching in Alder Ave
Forming for Hops Alley trash enclosure