11/13/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 11/07/2025:

  • Irrigation in Hops Alley
  • Landscaping in Hops Alley
  • Prep & pour concrete pavement in the park

WORK IN PROGRESS THIS WEEK (11/10/2025 - 11/14/2025):

  • Prep and pour Alder driveway approach & sidewalk
  • Continue Landscaping in Hops Alley
  • Prep & pour concrete pavement in the park
  • Continue Irrigation in Heritage Park & Hops Alley

UPCOMING WORK THROUGH 12/05/2025:

  • Concrete Paving in Heritage Park
  • Install trash enclosure panels
  • Install Entry Sign in Heritage Park
  • Irrigation in Hops Alley & Heritage Park
  • Landscaping in Hops Alley
  • Cable Fence & Paver Installation in Hops Alley
  • Installation of Entry Sign in Heritage Park

Heritage Park Concrete

Alder Driveway approach & Sidewalk