10/22/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 10/17/2025:
- Electrical Underground work in Heritage Park
- Grading & Asphalt Paving in Hops Alley
- Electrical Work in Hops Alley
- Metal Planter bed installation in Hops Alley
WORK IN PROGRESS NEXT WEEK (10/20/2025 - 10/24/2025):
- Underground electrical work in Heritage Park
- Concrete in Hops Alley
- Irrigation in Hops Alley
UPCOMING WORK THROUGH 11/14/2025:
- Install metal planter beds in Heritage Park
- Concrete in Heritage Park
- Install Entry Sign Heritage Park
- Irrigation in Hops Alley & Heritage Park
- Landscaping in Hops Alley
- Cable Fence & Paver Installation in Hops Alley
Planter installation and Concrete & Asphalt in Hops Alley
Underground Electrical installation in Heritage Park