05/18/2023 - Construction Update
Work Completed Between 05/10/23 and 05/17/23:
Sewer:
- Worked through Sewer Main installation
- Tested Sewer connections to ensure flow
Storm:
- Worked through Strom Main installation
- Tested Storm connections to ensure flow
Temporary sewer bypass that was installed at the beginning of the project that ran along the east side of Wood Ave in front of Heritage Bank.
Work in Progress this Week between 05/18/23 and 05/24/23:
Sewer:
- Finishing the Sewer Main installation
- Removal of the Sewer Line bypass
Storm:
- Finishing the Storm Main installation
Water:
- Continuing to work on the Water Main installation
- Installation of new Water Services
- Water testing to ensure water is safe
Upcoming Work between 05/25/23 and 05/31/23:
* There will be no work on Monday 05/29/23 due to Memorial Day *
Storm:
- Adjustment of catch basins to match grade
Water:
- Continuation of water testing
- Water connection tie ins to be completed at night
Other:
- Start of the Joint Utility Trench to underground the overhead power and communication lines