06/08/2023 - Construction Update

Work Completed between 06/01/23 and 06/07/23:

Water:

  • Completed water tie ins to businesses

Dry Utilities:

  • Started the Joint Utility Trench (JUT) with excavation and placement of conduit for communication lines and power lines

06/05/23 - Start of the JUT in front of the Day and Night parking lot.


06/05/23 - Placement of the conduit that will hold the power and communication lines that currently run across Main St along the west side of Wood Ave.



Work in Progress this Week between 06/08/23 and 06/14/23:

Sewer:

  • Finishing up connections to businesses

Dry Utilities:

  • Finalization of the JUT and installation of the signal connections underground
  • Pour signal bases for new signal poles that will be installed later on during the project

Concrete Curb, Gutter, and Sidewalks:

  • Demolition of existing sidewalks for grading and preparation of new sidewalks


Upcoming Work between 06/15/23 and 06/21/23:

Dry Utilities:

  • Finalize the installation of the signal connections

Concrete Curb, Gutter, and Sidewalks:

  • Finalize the demolition and grading in preparation of the pouring of sidewalks
  • Pouring sidewalks, curb, and gutter (this will be completed as daytime work under traffic control)

Full intersection closure is expected to begin on Wednesday, July 5th.