06/01/2023 - Construction Update

Work Completed between 05/25/23 and 05/31/23:

*No work was done on Monday 05/29/23 due to Memorial Day*

Storm:

  • Completed storm drainage installation

Water:

  • Continued to work through the water main installation and tested the water


05/24/23 - Installation of maintenance hole for access to utility lines.


05/25/223 - Installation of water main within the intersection.



Work in Progress this Week between 06/01/23 and 06/07/23:

Water:

  • Make water connection tie ins to businesses

Dry Utilities:

  • Joint Utility Trench (JUT) work to begin with the removal of pavement to install conduit for the relocation of overhead power and communication lines
  • Signal bases will start to be prepared and poured (this will be day time work under traffic control)

Upcoming Work between 06/08/23 and 06/14/23:

Dry Utilities:

  • Finish JUT work and final inspection from PSE
  • Finish pouring signal pole bases

Concrete Curb, Gutter, and Sidewalk:

*This will be completed as daytime work under traffic control*

  • Demolition and grading for new curb and gutter
  • Pouring of concrete curbs
  • Prepping for the pour of concrete sidewalks