06/01/2023 - Construction Update
Work Completed between 05/25/23 and 05/31/23:
*No work was done on Monday 05/29/23 due to Memorial Day*
Storm:
- Completed storm drainage installation
Water:
- Continued to work through the water main installation and tested the water
05/24/23 - Installation of maintenance hole for access to utility lines.
05/25/223 - Installation of water main within the intersection.
Work in Progress this Week between 06/01/23 and 06/07/23:
Water:
- Make water connection tie ins to businesses
Dry Utilities:
- Joint Utility Trench (JUT) work to begin with the removal of pavement to install conduit for the relocation of overhead power and communication lines
- Signal bases will start to be prepared and poured (this will be day time work under traffic control)
Upcoming Work between 06/08/23 and 06/14/23:
Dry Utilities:
- Finish JUT work and final inspection from PSE
- Finish pouring signal pole bases
Concrete Curb, Gutter, and Sidewalk:
*This will be completed as daytime work under traffic control*
- Demolition and grading for new curb and gutter
- Pouring of concrete curbs
- Prepping for the pour of concrete sidewalks