Work Completed Between 05/18/23 and 05/24/23:

Sewer:

  • Completed sewer main installation and testing

Storm:

  • Continued storm drainage installation

Water:

  • Continued water main installation


Work in Progress this Week between 05/25/23 and 05/31/23:

* There will be no work the night of Monday 05/29/23 - Tuesday 05/30/23 due to Memorial Day *

Storm:

  • Completing the storm drainage installation

Water:

  • Continuing the water main installation, testing, tie-ins and service connections.

Dry Utilities:

  • Joint Utility Trench (JUT): Start demolition of pavement for installation of conduits to underground overhead power and communication lines
  • Signals: Start installing signal pole bases


Upcoming Work between 06/01/23 and 06/11/23:

Water:

  • Completing the water main tie-ins and service connections.

Dry Utilities:

  • Joint Utility Trench (JUT): Continue demolition of pavement for installation of conduits to underground overhead power and communication lines
  • Signals: Continue installing signal pole bases

Concrete Curb, Gutter, and Sidewalk (Day time work under traffic control):

  • Demolition and grading for curb and gutter
  • Pour concrete curbs
  • Prep and pour for concrete sidewalks