05/26/2023 - Construction Update
Work Completed Between 05/18/23 and 05/24/23:
Sewer:
- Completed sewer main installation and testing
Storm:
- Continued storm drainage installation
Water:
- Continued water main installation
Work in Progress this Week between 05/25/23 and 05/31/23:
* There will be no work the night of Monday 05/29/23 - Tuesday 05/30/23 due to Memorial Day *
Storm:
- Completing the storm drainage installation
Water:
- Continuing the water main installation, testing, tie-ins and service connections.
Dry Utilities:
- Joint Utility Trench (JUT): Start demolition of pavement for installation of conduits to underground overhead power and communication lines
- Signals: Start installing signal pole bases
Upcoming Work between 06/01/23 and 06/11/23:
Water:
- Completing the water main tie-ins and service connections.
Dry Utilities:
- Joint Utility Trench (JUT): Continue demolition of pavement for installation of conduits to underground overhead power and communication lines
- Signals: Continue installing signal pole bases
Concrete Curb, Gutter, and Sidewalk (Day time work under traffic control):
- Demolition and grading for curb and gutter
- Pour concrete curbs
- Prep and pour for concrete sidewalks