05/11/2023 - Construction Update

Work Completed between 05/01/23 and 05/09/23:

Sewer:

  • Sewer Bypass installation has been completed to allow for new Sewer Main lines to be installed
  • Sewer Main installations are nearing completion

Storm:

  • Storm Main installations are nearing completion

Other:

  • Temporary re-channelization of intersection completed to allow for onsite equipment staging
  • PSE removed two luminaires that were in the way of a new storm connection


05/08/2023 - Digging to access sewer main line for replacement in the Main and Wood intersection in front of Heritage Bank.


05/08/2023 - Removing steel plates and temporary patch from the previous night's work.



Work in Progress this Week between 05/10/23 and 05/16/23:

Sewer:

  • Finishing of the Sewer Main installations with testing of connections
  • Removal of Sewer Bypass

Storm:

  • Finishing of the Storm Main installations

Water:

  • Water Main installation anticipated to start Wednesday night (05/16)


Upcoming Work between 05/17/23 and 05/23/23

Water:

  • Work through Water Main installation and water testing before service connections