05/11/2023 - Construction Update
Work Completed between 05/01/23 and 05/09/23:
Sewer:
- Sewer Bypass installation has been completed to allow for new Sewer Main lines to be installed
- Sewer Main installations are nearing completion
Storm:
- Storm Main installations are nearing completion
Other:
- Temporary re-channelization of intersection completed to allow for onsite equipment staging
- PSE removed two luminaires that were in the way of a new storm connection
05/08/2023 - Digging to access sewer main line for replacement in the Main and Wood intersection in front of Heritage Bank.
05/08/2023 - Removing steel plates and temporary patch from the previous night's work.
Work in Progress this Week between 05/10/23 and 05/16/23:
Sewer:
- Finishing of the Sewer Main installations with testing of connections
- Removal of Sewer Bypass
Storm:
- Finishing of the Storm Main installations
Water:
- Water Main installation anticipated to start Wednesday night (05/16)
Upcoming Work between 05/17/23 and 05/23/23
Water:
- Work through Water Main installation and water testing before service connections