Anticipated Construction Schedule

Construction on the Main and Wood intersection is scheduled to begin on Monday May 1st. A preliminary construction schedule can be found below:


Phase 1 - Utilities and Sidewalks (Night Closure) May 2023 - June 2023
Phase 2 - Paving of Intersection (24/7 Closure) June 2023 - July 2023
Phase 3 - Landscaping and Site Furnishings (Intersection Open) July 2023
Phase 4 - Signal Pole Installation (Intersection Open) Spring 2024


If any adjustments and timelines shift, an update will be given with the most up to date and current schedule. Weekly progress updates will also be given.