Planting and Utilities
Just a quick update - while we await the 2026 fish window, the only work occurring is the relocation of critical power to a safer location outside of our new floodplain and the planting of trees. The project has relocated water, sewer, gas, power, and communication lines. The final pieces are these transmission poles. Once done, we can work to complete the connection of the middle river side channel later this year. The planting is additionally occurring now. We have over 500,000 plants which will be installed between this year and next. Rodarte and their sub-contractor Ash Creek and working on the first batch of these plants now.