Washington St Preservation Project
The project work includes replacing failing pavement, curbs, gutters, and sidewalks, upgrading underground utilities such as sanitary sewer, water, and storm drainage systems, and making accessibility improvements to meet current ADA standards.
The project work includes replacing failing pavement, curbs, gutters, and sidewalks, upgrading underground utilities such as sanitary sewer, water, and storm drainage systems, and making accessibility improvements to meet current ADA standards.
-
07/28/2026 Construction Update
Work completed:
Contractor mobilized and began installation of underground utilities in Washington St between Wood Ave and McMillan Ave.
Work this week:
Continue installation of underground utilities.
Upcoming work:
Installation of dewatering system.
Complete settlement monitoring survey.
Continue installation of underground utilities.
Work completed:
Contractor mobilized and began installation of underground utilities in Washington St between Wood Ave and McMillan Ave.
Work this week:
Continue installation of underground utilities.
Upcoming work:
Installation of dewatering system.
Complete settlement monitoring survey.
Continue installation of underground utilities.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends
No thanks -
07/07/2026 Neighborhood Meeting
The City is hosting a neighborhood meeting to update the community on the project and a rough project timeline. The meeting is on Tuesday 07/07/2026 at 6:00 pm at City Hall in City Council Chambers. A letter were mailed to residents regarding this meeting.
The City is hosting a neighborhood meeting to update the community on the project and a rough project timeline. The meeting is on Tuesday 07/07/2026 at 6:00 pm at City Hall in City Council Chambers. A letter were mailed to residents regarding this meeting.
-
News Feed
Project is out to Bid on March 4, 2026
Project is out to Bid on March 4, 2026
-
Phone (253) 299-5703 Email alisao@sumnerwa.gov
-
Design Consultant Selection
Washington St Preservation Project has finished this stageThe design consultant was selected through a Request for Qualifications (RFQ) process. The selected design consultant is KPG Psomas.
-
Design & Permitting
Washington St Preservation Project has finished this stagePermitting is complete. Design is currently underway and is expected to be completed in February of 2026.
-
Public Meeting
Washington St Preservation Project has finished this stageA Public meeting with homeowner was held on February 11, 2026.
-
Construction Bidding
Washington St Preservation Project has finished this stageProject is out to Bid on March 4, 2026
-
Construction Bids
Washington St Preservation Project has finished this stageBids are due until 1:00 PM Tuesday, March 31, 2026. Just after 1:00 p.m., bids will be formally opened and publicly read aloud in the City Council Chambers, located on the first floor of Sumner City Hall.
-
Construction Contract award
Washington St Preservation Project has finished this stageConstruction Contract awarded to Miles Resources, LLC.
-
Second Public Meeting
Washington St Preservation Project is currently at this stageA second Public meeting is scheduled for July 7, 2026 at 6PM in the Sumner City Hall Council Chambers.
-
Construction
this is an upcoming stage for Washington St Preservation ProjectContractor to begin work in late July.