4/03/2023 Construction Update
WORK COMPLETED FOR WEEK ENDING 03/31/2023
- Kincaid (Maple to Main)
- Complete installation of Bollards
- Complete install of truncated domes
- Complete driveway from alleyway
- Cherry Avenue (Maple to Main)
- Complete water tie in at Cherry/Maple
- Temporary Pave for Daffodil Parade on 4/1
- Alder Avenue (Park to Maple)
- Temporary Pave for Daffodil Parade on 4/1
- Academy Street (Alder to Ryan)
- Temp Pave for Daffodil Parade on 4/1
- Continue concrete flat work and ramps
WORK IN PROGRESS THIS WEEK (4/03/2023 - 04/07/2023)
- Park and Alder Intersection
- Begin Demolition
- Continue storm system
- Cherry Street
- Begin Storm testing
- Begin illumination system
- Cherry Street / Maple Street Intersection
- Begin water testing
- Begin installation of Storm System
- Main Street
- Westbound Only - from Alder Avenue to Traffic Avenue
- Eastbound local access from Traffic Avenue to BNSF
- Begin Demolition
- Begin installation of Storm System
- Academy Street (Alder to Ryan)
- Continue concrete flat work and ramps
UPCOMING WORK THROUGH (04/21/2023)
- Park and Alder Intersection
- Begin water transfers
- Begin water tie in's
- Cherry Street
- Begin installation of irrigation sleeves
- Begin roadway excavation
- Begin CSBC
- Cherry Street / Maple Street Intersection
- Begin water tie in's on Maple Street
- Begin Roadway Excavation
- Begin CSBC
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Main Street
- Begin Power and Fiber
- Begin installation of irrigation sleeves
- Begin Roadway Excavation
- Begin CSBC
- Academy Street (Alder to Ryan)
- Complete trench restoration