3/27/2023 Construction Update
Work Completed for Week ending 03/24/2023
- Kincaid (Maple to Main)
- Begin Bollard Installation
- Cherry Avenue (Maple to Main)
- Complete installing storm drainage.
- Complete installing joint utility trench
- Academy Street (Alder to Ryan)
- Complete installing storm drainage
- Continue Road excavation / gravel borrow and csbc
- Complete curb and gutter
- Continue concrete flat work and ramps
- Complete water tie in at Academy/Alder intersection
Work in progress this week (3/28/2023 - 3/31/2023)
- Kincaid (Maple to Main)
- Continue installation of Bollards
- Complete install of truncated domes
- Complete driveway from alleyway
- Cherry Avenue (Maple to Main)
- Complete water tie in at Cherry/Maple
- Temp Pave for Daffodil Parade on 4/1
- Alder Avenue (Park to Maple)
- Temp Pave for Daffodil Parade on 4/1
- Academy Street (Alder to Ryan)
- Temp Pave for Daffodil Parade on 4/1
- Continue concrete flat work and ramps
Upcoming Work through (04/14/2023) - Work on Main Street will not begin until after the Daffodil Parade (04/01/23)
- Academy Street (Alder to Ryan)
- Complete trench restoration
- Cherry Avenue (Maple to Main)
- Complete Illumination
- Begin irrigation
- Communications companies will need to relocate services from old poles to new poles before the old poles can be removed.
- Maple/Cherry intersection
- Complete installing water main
- Complete water tie-in
- Alder Ave / Park Street intersection
- Complete demolition
- Complete storm drainage installation
- Begin water tie-in
- Main Street / Cherry Avenue / Kincaid Avenue intersection
- Main Street in westbound only condition from Alder Avenue to Traffic Avenue (eastbound local access from Traffic Avenue to BNSF)
- Begin demolition on south side
- Begin installation of storm drainage