6/26/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 06/27/2025:

  • Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
  • Survey and dig footings for Concrete Seat wall in Heritage Park
  • Dig, Form and Pour Concrete for Umbrella foundations in Heritage Park

WORK IN PROGRESS NEXT WEEK (06/30/2025 - 07/4/2025):

  • Begin installation of Silva Cell System in Hops Alley
  • Excavate footings, set forms, and install rebar for the concrete seat wall in Heritage Park
  • Begin Stormwater work in Hops Alley & Heritage Park

UPCOMING WORK THROUGH 07/25/2025:

**KINCAID CLOSURE - Postponed to after Rhubarb Day, tentatively planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)

  • Install Water Services in Hops Alley
  • Install bollard foundations in Hops Alley
  • Pour concrete for the Heritage Park seat wall


Digging footings for Concrete Seat wall in Heritage Park

Concrete Pour for Pole Foundations in Hops Alley