6/26/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 06/27/2025:
- Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
- Survey and dig footings for Concrete Seat wall in Heritage Park
- Dig, Form and Pour Concrete for Umbrella foundations in Heritage Park
WORK IN PROGRESS NEXT WEEK (06/30/2025 - 07/4/2025):
- Begin installation of Silva Cell System in Hops Alley
- Excavate footings, set forms, and install rebar for the concrete seat wall in Heritage Park
- Begin Stormwater work in Hops Alley & Heritage Park
UPCOMING WORK THROUGH 07/25/2025:
**KINCAID CLOSURE - Postponed to after Rhubarb Day, tentatively planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Install Water Services in Hops Alley
- Install bollard foundations in Hops Alley
- Pour concrete for the Heritage Park seat wall