6/18/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 06/20/2025:
- Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
- Begin Survey and dig footings for Concrete Seat wall in Heritage Park
WORK IN PROGRESS NEXT WEEK (06/23/2025 - 06/27/2025):
- Complete Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
- Begin installation of Silva Cell System in Hops Alley
- Footings, form, rebar, and pour concrete for Concrete Seat wall in Heritage Park
UPCOMING WORK THROUGH 07/25/2025:
**KINCAID CLOSURE - Postponed to after Rhubarb Day, tentatively planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Begin Stormwater work in Hops Alley & Heritage Park
- Install Water Services in Hops Alley
- Dig, Form and Pour Concrete for Umbrella foundations in Heritage Park