6/13/2025 CONSTRUCTION UPDATE

WORK COMPLETED FOR WEEK ENDING 06/06/2025:

  • Hops Alley Sewer Install
  • Start Deep Pole Foundation Work for Overhead Lighting System in Heritage Park

WORK IN PROGRESS NEXT WEEK (06/09/2025 - 06/13/2025):

  • Start Deep Pole Foundation Work for Overhead Lighting System in Hops Alley
  • Complete Hops Alley Sewer install
  • Complete Deep Pole Foundation Work for Overhead Lighting System in Heritage Park

UPCOMING WORK THROUGH 07/04/2025:

  • KINCAID CLOSURE - Postponed to after Rhubarb Days
  • Grade, install rebar and pour concrete
  • Silva Cell System install in Hops Alley
  • Stormwater install in Hops Alley
  • Survey, Footings, form, rebar, and pour concrete for Concrete Seat wall in Heritage Park

Deep Pole Foundations in Heritage Park for New Overhead Lighting System

Getting ready for new Sewer in Hops Alley