5/22/2025 CONSTRUCTION UPDATE
WORK COMPLETED FOR WEEK ENDING 05/16/2025:
- Civil Underground Demolition and Excavation
- Pothole Utilities
- Water Main excavation in Hops Alley
WORK IN PROGRESS NEXT WEEK (05/27/2025 - 05/30/2025):
**5/27/2025 - KINCAID AVE CLOSURE starting at 7:00am**
**5/30/2025 - Kincaid Ave Open**
- Pressure Test Water Main & Purity Test
- Sawcut and Demo Concrete on Kincaid Ave
- Install Sewer manhole on Kincaid Ave
- Watermain tie in on Kincaid Ave
- Hops Alley Sewer install
UPCOMING WORK THROUGH 06/13/2025:
- Sawcut, Demo and install waterline in Alder Ave
- Deep Pole Foundation Work for Overhead Lighting System in Heritage Park & Hops Alley