5/22/2025 CONSTRUCTION UPDATE

WORK COMPLETED FOR WEEK ENDING 05/16/2025:

  • Civil Underground Demolition and Excavation
  • Pothole Utilities
  • Water Main excavation in Hops Alley


WORK IN PROGRESS NEXT WEEK (05/27/2025 - 05/30/2025):

**5/27/2025 - KINCAID AVE CLOSURE starting at 7:00am**

**5/30/2025 - Kincaid Ave Open**

  • Pressure Test Water Main & Purity Test
  • Sawcut and Demo Concrete on Kincaid Ave
  • Install Sewer manhole on Kincaid Ave
  • Watermain tie in on Kincaid Ave
  • Hops Alley Sewer install


UPCOMING WORK THROUGH 06/13/2025:

  • Sawcut, Demo and install waterline in Alder Ave
  • Deep Pole Foundation Work for Overhead Lighting System in Heritage Park & Hops Alley