5/14/2025 CONSTRUCTION UPDATE

WORK COMPLETED FOR WEEK ENDING 05/09/2025:

  • Demolition Work in Heritage Park
  • Demotion Work in Hops Alley
  • Pothole Utilities
  • Water Line Locates

WORK IN PROGRESS THIS WEEK (05/12/2025 - 05/16/2025):

  • Civil Underground Demolition and Excavation
  • Pothole Utilities
  • Water Main excavation in Hops Alley

UPCOMING WORK THROUGH 05/31/2025:

  • Water Main install in Hops Alley (includes connection in Kincaid Ave & Alder Ave)
  • Sewer Main in Hops Alley (Includes connection in Kincaid Ave)
  • Deep Pole Foundation Work for Overhead Lighting System in Heritage Park