5/14/2025 CONSTRUCTION UPDATE
WORK COMPLETED FOR WEEK ENDING 05/09/2025:
- Demolition Work in Heritage Park
- Demotion Work in Hops Alley
- Pothole Utilities
- Water Line Locates
WORK IN PROGRESS THIS WEEK (05/12/2025 - 05/16/2025):
- Civil Underground Demolition and Excavation
- Pothole Utilities
- Water Main excavation in Hops Alley
UPCOMING WORK THROUGH 05/31/2025:
- Water Main install in Hops Alley (includes connection in Kincaid Ave & Alder Ave)
- Sewer Main in Hops Alley (Includes connection in Kincaid Ave)
- Deep Pole Foundation Work for Overhead Lighting System in Heritage Park