09/12/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 09/12/2025:
- Performed underground electrical work in Heritage Park
- Connected Hops Alley to water main in Alder Ave
- Start Stormwater work in Heritage Park
- Set forms for trash enclosure in Hops Alley
WORK IN PROGRESS NEXT WEEK (09/15/2025 - 09/19/2025):
**Alder Ave will have roadwork occurring with traffic control to complete road restoration until 9/30
- Perform underground electrical work in Heritage Park
- Continue Stormwater work in Heritage Park
- Pour concrete footings for trash enclosure in Hops Alley
- Install irrigation sleeves in Hops Alley
- Complete Water Service connections in Hops Alley
UPCOMING WORK THROUGH 09/30/2025:
- Install metal planter beds in Heritage Park and Hops Alley
- Install irrigation system in Hops Alley
- Concrete paving and curb construction in Hops Alley
- Asphalt paving in Hops Alley