09/12/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 09/12/2025:

  • Performed underground electrical work in Heritage Park
  • Connected Hops Alley to water main in Alder Ave
  • Start Stormwater work in Heritage Park
  • Set forms for trash enclosure in Hops Alley

WORK IN PROGRESS NEXT WEEK (09/15/2025 - 09/19/2025):

**Alder Ave will have roadwork occurring with traffic control to complete road restoration until 9/30

  • Perform underground electrical work in Heritage Park
  • Continue Stormwater work in Heritage Park
  • Pour concrete footings for trash enclosure in Hops Alley
  • Install irrigation sleeves in Hops Alley
  • Complete Water Service connections in Hops Alley

UPCOMING WORK THROUGH 09/30/2025:

  • Install metal planter beds in Heritage Park and Hops Alley
  • Install irrigation system in Hops Alley
  • Concrete paving and curb construction in Hops Alley
  • Asphalt paving in Hops Alley


Connecting Hops Alley to water main in Alder Ave