09/05/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 09/05/2025:

  • Performed underground electrical work in Heritage Park and Hops Alley.
  • Installed electrical components within the Heritage Park seat wall
  • Poured concrete for the Heritage Park seat wall
  • Stormwater work in Heritage Park

WORK IN PROGRESS NEXT WEEK (09/08/2025 - 09/12/2025):

**ALDER AVE CLOSURE – planned for September 9th, from 8:00P.M. to 8:00 a.m., to complete the Hops Alley water main connection.

**Additionally, Alder Ave will have roadwork occurring with traffic control to complete road restoration until 9/30

  • Perform underground electrical work in Heritage Park
  • Stormwater work in Heritage Park
  • Start forming for trash enclosure in Hops Alley

UPCOMING WORK THROUGH 09/30/2025:

  • Install metal planter beds in Heritage Park and Hops Alley
  • Install irrigation system in Hops Alley
  • Concrete paving and curb construction in Hops Alley
  • Asphalt paving in Hops Alley


Heritage Park concrete seat wall




#<Object:0x000000003c5b5a40>