08/21/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/21/2025:
- Performed underground electrical work in Hops Alley
- Installed Silva Cell systems in Hops Alley
- Installed water services in Hops Alley
WORK IN PROGRESS NEXT WEEK (08/25/2025 - 08/29/2025):
- Restore north sidewalk in Hops Alley (scheduled for 8/27–8/28)
- Stormwater work in Heritage Park
- Install electrical components within the Heritage Park seat wall
- Pour concrete for Heritage Park seat wall
UPCOMING WORK THROUGH 09/30/2025:
- Perform underground electrical work in Heritage Park
- Connect Hops Alley to water main in Alder Ave
- Install metal planter beds in Heritage Park and Hops Alley
- Install irrigation system in Hops Alley
North sidewalk concrete pour plan