08/14/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/15/2025:
- Set forms and installed additional rebar for the Heritage Park seat wall
- Stormwater improvements in Hops Alley
- Installed Silva Cell systems in Hops Alley
- Installed irrigation sleeves in Hops Alley
- Installed water services in Hops Alley
WORK IN PROGRESS NEXT WEEK (08/18/2025 - 08/22/2025):
- Pour concrete for Heritage Park seat wall
- Stormwater work in Heritage Park
- Install Silva Cell systems in Hops Alley
- Install electrical components within the Heritage Park seat wall
- Perform underground electrical work in Hops Alley
UPCOMING WORK THROUGH 08/29/2025:
- Perform underground electrical work in Heritage Park
- Restore north sidewalk in Hops Alley (scheduled for 8/27–8/28)
North sidewalk concrete pour plan
Installation of water services in Hops Alley
Trenching in Hops Alley