08/14/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 08/15/2025:

  • Set forms and installed additional rebar for the Heritage Park seat wall
  • Stormwater improvements in Hops Alley
  • Installed Silva Cell systems in Hops Alley
  • Installed irrigation sleeves in Hops Alley
  • Installed water services in Hops Alley

WORK IN PROGRESS NEXT WEEK (08/18/2025 - 08/22/2025):

  • Pour concrete for Heritage Park seat wall
  • Stormwater work in Heritage Park
  • Install Silva Cell systems in Hops Alley
  • Install electrical components within the Heritage Park seat wall
  • Perform underground electrical work in Hops Alley

UPCOMING WORK THROUGH 08/29/2025:

  • Perform underground electrical work in Heritage Park
  • Restore north sidewalk in Hops Alley (scheduled for 8/27–8/28)

North sidewalk concrete pour plan

Installation of water services in Hops Alley

Trenching in Hops Alley