08/07/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/08/2025:
- Set forms and installed additional rebar for the Heritage Park seat wall
- Completed stormwater improvements in Hops Alley
- Installed Silva Cell system in Hops Alley
- Installed irrigation sleeves in Hops Alley
WORK IN PROGRESS NEXT WEEK (08/11/2025 - 08/15/2025):
- Pour concrete for Heritage Park seat wall
- Stormwater work in Heritage Park
- Install additional Silva Cell systems in Hops Alley
- Install additional irrigation sleeves in Hops Alley
- Install electrical components within the Heritage Park seat wall
UPCOMING WORK THROUGH 08/29/2025:
- Install Water Services in Hops Alley
- Perform underground electrical work in both Hops Alley and Heritage Park
- Restore north sidewalk in Hops Alley (scheduled for 8/27–8/28)