07/31/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 07/31/2025:

**KINCAID CLOSURE – July 16–28 (Road reopened Monday morning, July 28)

  • Set forms and installed additional rebar for the Heritage Park seat wall
  • Continued stormwater improvements in Hops Alley

WORK IN PROGRESS NEXT WEEK (08/04/2025 - 08/08/2025):

  • Set forms and install rebar for the concrete seat wall in Heritage Park
  • Install electrical components within the Heritage Park seat wall
  • Ongoing stormwater work in Hops Alley and Heritage Park
  • Install Silva Cell system in Hops Alley
  • Install irrigation sleeves in Hops Alley

UPCOMING WORK THROUGH 08/29/2025:

  • Install Water Services in Hops Alley
  • Perform underground electrical work in both Hops Alley and Heritage Park
  • Pour concrete for the Heritage Park seat wall

Rebar and forms for the concrete seat wall in Heritage Park

Roadway Restoration Completed on Kincaid Street