07/31/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/31/2025:
**KINCAID CLOSURE – July 16–28 (Road reopened Monday morning, July 28)
- Set forms and installed additional rebar for the Heritage Park seat wall
- Continued stormwater improvements in Hops Alley
WORK IN PROGRESS NEXT WEEK (08/04/2025 - 08/08/2025):
- Set forms and install rebar for the concrete seat wall in Heritage Park
- Install electrical components within the Heritage Park seat wall
- Ongoing stormwater work in Hops Alley and Heritage Park
- Install Silva Cell system in Hops Alley
- Install irrigation sleeves in Hops Alley
UPCOMING WORK THROUGH 08/29/2025:
- Install Water Services in Hops Alley
- Perform underground electrical work in both Hops Alley and Heritage Park
- Pour concrete for the Heritage Park seat wall
Rebar and forms for the concrete seat wall in Heritage Park
Roadway Restoration Completed on Kincaid Street