07/24/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/25/2025:
- Poured footings and installed additional rebar for the Heritage Park seat wall
- Stormwater work in Hops Alley
- Poured concrete to restore the roadway surface on Kincaid Street
WORK IN PROGRESS NEXT WEEK (07/28/2025 - 08/01/2025):
**KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Ongoing stormwater work in Hops Alley and Heritage Park
- Set forms and install rebar for the concrete seat wall in Heritage Park
- Pour Concrete footing for seat wall in Heritage Park
UPCOMING WORK THROUGH 08/28/2025:
- Install Water Services in Hops Alley
- Install Silva Cell system in Hops Alley
- Perform underground electrical work in both Hops Alley and Heritage Park
- Install electrical components within the Heritage Park seat wall
- Pour concrete for the Heritage Park seat wall
Concrete pour underway on Kincaid Street as crews restore roadway surface following underground utility work.

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends