07/17/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/18/2025:
- Set forms and installed rebar for the concrete seat wall in Heritage Park
- Stormwater work in Hops Alley
- Installed bollard sockets in Hops Alley
WORK IN PROGRESS NEXT WEEK (07/21/2025 - 07/25/2025):
**KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Pour concrete to restore the roadway surface on Kincaid Street
- Pour footings and install additional rebar for the Heritage Park seat wall
- Ongoing stormwater work in Hops Alley
UPCOMING WORK THROUGH 08/28/2025:
- Install Water Services in Hops Alley
- Install Silva Cell system in Hops Alley
- Perform underground electrical work in both Hops Alley and Heritage Park
- Install electrical components within the Heritage Park seat wall
- Pour concrete for the Heritage Park seat wall
Stormwater work in Hops Alley
Forms and Rebar for Concrete seat wall in Heritage Park