07/17/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 07/18/2025:

  • Set forms and installed rebar for the concrete seat wall in Heritage Park
  • Stormwater work in Hops Alley
  • Installed bollard sockets in Hops Alley

WORK IN PROGRESS NEXT WEEK (07/21/2025 - 07/25/2025):

**KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)

  • Pour concrete to restore the roadway surface on Kincaid Street
  • Pour footings and install additional rebar for the Heritage Park seat wall
  • Ongoing stormwater work in Hops Alley

UPCOMING WORK THROUGH 08/28/2025:

  • Install Water Services in Hops Alley
  • Install Silva Cell system in Hops Alley
  • Perform underground electrical work in both Hops Alley and Heritage Park
  • Install electrical components within the Heritage Park seat wall
  • Pour concrete for the Heritage Park seat wall
    Stormwater work in Hops Alley
    Forms and Rebar for Concrete seat wall in Heritage Park
#<Object:0x00000000407a3718>