07/10/2025 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/11/2025:
- Set forms and installed rebar for the concrete seat wall in Heritage Park
- Stormwater work in Hops Alley
WORK IN PROGRESS NEXT WEEK (07/14/2025 - 07/18/2025):
- Pour footings, and install additional rebar for the concrete seat wall in Heritage Park
- Begin installation of electrical equipment within the seat wall
- Ongoing stormwater work in Hops Alley
- Install Silva Cell system in Hops Alley
- Install bollard sockets in Hops Alley
UPCOMING WORK THROUGH 07/25/2025:
**KINCAID CLOSURE - planned for July 7/16-7/28 (With Road opening on Monday morning 7/28)
- Install Water Services in Hops Alley
- Pour concrete for the Heritage Park seat wall
- Stormwater work in Heritage Park