8/1/2025 Construction Update

  • WORK COMPLETED FOR WEEK ENDING 08/01/2025:

  • Drive temporary sheet piles at north side trestle access
  • Drive temporary 36" pipe pile at the south trestle access
  • Backfilled northern trestle access for pier 2
  • Installed reaction frame for drilling permanent bridge shafts at pier 2
  • Made dewatering connections
  • Drilled and poured pier 3 shaft
  • WORK IN PROGRESS NEXT WEEK (08/03/2025 - 08/09/2025):

    • Continue driving 36" pile for southern trestle access
    • Begin drilling and pouring pier 2 shaft


  • UPCOMING WORK THROUGH 09/30/2025:

    • In-water work will commence until end of fish window.
    • Brief traffic interruptions will occur during crane operations. Traffic impacts expected to be minimal.

Pouring Pier 3 Shaft

View of Northern Trestle