WORK COMPLETED FOR WEEK ENDING 08/01/2025:
- Drive temporary sheet piles at north side trestle access
- Drive temporary 36" pipe pile at the south trestle access
- Backfilled northern trestle access for pier 2
- Installed reaction frame for drilling permanent bridge shafts at pier 2
- Made dewatering connections
- Drilled and poured pier 3 shaft
-
WORK IN PROGRESS NEXT WEEK (08/03/2025 - 08/09/2025):
- Continue driving 36" pile for southern trestle access
- Begin drilling and pouring pier 2 shaft
-
UPCOMING WORK THROUGH 09/30/2025:
- In-water work will commence until end of fish window.
- Brief traffic interruptions will occur during crane operations. Traffic impacts expected to be minimal.