12/19/2025 Construction Update
-
WORK COMPLETED FOR WEEK ENDING 12/20/2025:
- Poured span 2 concrete bridge deck
- Continued work on bridge deck formwork
- Continued surcharge settlement period
-
WORK IN PROGRESS NEXT WEEK (12/21/2025 - 12/27/2025):
- Continue bridge deck rebar installation
- Continued work on bridge deck formwork
- Pour concrete span 1 bridge deck weather permitting
-
UPCOMING WORK THROUGH 12/30/2025:
- Work will continue on new bridge substructure and bridge deck.
- Surcharge settlement period will be 2 months
Installing Bidwell
Placing concrete deck at span 2