12/19/2025 Construction Update

  • WORK COMPLETED FOR WEEK ENDING 12/20/2025:

    • Poured span 2 concrete bridge deck
    • Continued work on bridge deck formwork
    • Continued surcharge settlement period
  • WORK IN PROGRESS NEXT WEEK (12/21/2025 - 12/27/2025):

    • Continue bridge deck rebar installation
    • Continued work on bridge deck formwork
    • Pour concrete span 1 bridge deck weather permitting
  • UPCOMING WORK THROUGH 12/30/2025:

    • Work will continue on new bridge substructure and bridge deck.
    • Surcharge settlement period will be 2 months

Installing Bidwell

Placing concrete deck at span 2